252
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
NT0034 #07 Y:2024 | 07 | 2024 | Purchase new equipment to reduce material use / cost | $30,115 | $80,000 |
n/a
|
UW2414 #09 Y:2024 | 09 | 2024 | Purchase new equipment to reduce material use / cost | $252,286 | $90,000 |
n/a
|
OR0801 #01 Y:2024 | 01 | 2024 | Modify process to reduce material use/cost | $1,848 | - |
n/a
|
LS2413 #02 Y:2024 | 02 | 2024 | Modify process to reduce material use/cost | $5,076 | $16,000 |
n/a
|
SF0619 #11 Y:2024 | 11 | 2024 | Purchase new equipment to reduce material use / cost | $52,391 | $160,125 |
n/a
|
OR0784 #02 Y:2023 | 02 | 2023 | Modify process to reduce material use/cost | $343,134 | $700,000 | |
MUWT04 #07 Y:2023 | 07 | 2023 | Modify process to reduce material use/cost | $85,324 | - | |
MZ0326 #08 Y:2022 | 08 | 2022 | Purchase new equipment to reduce material use / cost | $116,541 | $552,315 | |
NL0066 #03 Y:2022 | 03 | 2022 | Purchase new equipment to reduce material use / cost | $49,500 | $95,000 | |
TT0280 #01 Y:2022 | 01 | 2022 | Modify process to reduce material use/cost | $52,932 | $4,800 | |
AS0523 #01 Y:2022 | 01 | 2022 | Purchase new equipment to reduce material use / cost | $42,697 | $89,337 | |
LS2215 #02 Y:2022 | 02 | 2022 | Purchase new equipment to reduce material use / cost | $9,603 | $1,118 | |
MZ0316 #05 Y:2021 | 05 | 2021 | Purchase new equipment to reduce material use / cost | $12,219 | $40,130 | |
MZ0296 #07 Y:2020 | 07 | 2020 | Purchase new equipment to reduce material use / cost | $57,876 | $199,418 | |
MZ0296 #06 Y:2020 | 06 | 2020 | Purchase new equipment to reduce material use / cost | $100,865 | $197,145 | |
MZ0285 #03 Y:2019 | 03 | 2019 | Purchase new equipment to reduce material use / cost | $66,439 | $129,987 | |
OR0725 #01 Y:2019 | 01 | 2019 | Modify process to reduce material use/cost | $16,581 | $12,780 | |
OR0722 #01 Y:2019 | 01 | 2019 | Modify process to reduce material use/cost | $42,047 | $1,000 | |
MZ0282 #05 Y:2019 | 05 | 2019 | Purchase new equipment to reduce material use / cost | $287,984 | $1,030,500 | |
MZ0272 #07 Y:2019 | 07 | 2019 | Purchase new equipment to reduce material use / cost | $31,952 | $68,000 |