ITAC Assessment: MZ0282
ITAC logo
ITAC Assessment: MZ0282
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product radiators and power train cooling modules
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $100
M
to 500
M
# of Employees 218
Plant Area 163,000
ft2
Annual Production 190,000
pieces
Production Hrs. Annual 7,224
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $598,949 9,620,533
kWh
Electricity Demand $245,294 20,459
kW-mo/yr
Natural Gas $475,875 226,379
MMBtu
Waste Disposal Costs
Water Usage $15,222 470,442
Tgal
Water Disposal $14,249 470
Tgal
TOTAL YEARLY COSTS $1,349,588
RECOMMENDED SAVINGS* $379,467 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $65,526

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7144: Install spectral reflectors / delamp $586 $472 $268
4,298
kWh
$257
-
kW-mo/yr
- - - $61
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $6,947 $24,000 $5,307
85,604
kWh
$1,640
-
kW-mo/yr
- - - -
03 2.4221: Install compressor air intakes in coolest locations $4,896 $2,300 $3,676
61,267
kWh
$1,220
-
kW-mo/yr
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,849 $320 $1,399
22,570
kWh
$450
-
kW-mo/yr
- - - -
05 4.132: Purchase new equipment to reduce material use / cost $287,984 $1,030,500 $(-100,775.0)
(-1,625,400)
kWh
$(-40,427.0)
-
kW-mo/yr
- - $429,186 -
06 2.2442: Preheat combustion air with waste heat $3,100 $14,000 - - $3,100
-
MMBtu
- - -
07 2.2437: Recover waste heat from equipment $7,721 $7,200 - - $7,721
-
MMBtu
- - -
08 2.7447: Install vinyl strip / high speed / air curtain doors $53,310 $16,200 $(-1,278.0)
(-20,164)
kWh
$(-480.0)
-
kW-mo/yr
$55,068
-
MMBtu
- - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,909 $680 $2,789
44,987
kWh
$1,120
-
kW-mo/yr
- - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $3,466 $2,964 $3,466
55,896
kWh
- - - - -
11 3.4116: Meter recycled water (to reduce sewer charges) $5,699 $18,720 - - - $5,699
-
Tgal
- -
TOTAL RECOMMENDED $379,467 $1,117,356 $(-85,148.0)
(-1,370,942)
kWh
$(-36,220.0)
-
kW-mo/yr
$65,889
-
MMBtu
$5,699
-
Tgal
$429,186 $61
TOTAL IMPLEMENTED $65,526 $24,552 $1,779
29,121
kWh
$897
-
kW-mo/yr
$62,789
-
MMBtu
- - $61
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs