ITAC Assessment: UW2414
ITAC logo
ITAC Assessment: UW2414
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Beer, Cider
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $1
M
to 5
M
# of Employees 15
Plant Area 17,500
ft2
Annual Production 492
Tgal
Production Hrs. Annual 5,110
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,298 580,556
kWh
Electricity Demand $7,248 1,252
kW-mo/yr
Electricity Fees $5,995 -
Natural Gas $31,410 2,834
MMBtu
LPG $1,731 78
MMBtu
Other Gas $15,266 1
MMBtu
Waste Disposal Costs
Water Usage $7,000 2,820
Tgal
Water Disposal $15,666 2,820
Tgal
Gaseous Waste $57,096 143,890
lb
TOTAL YEARLY COSTS $207,708
RECOMMENDED SAVINGS* $535,979 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings Increase in Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $141 $220 $126
1,104
kWh
$15
-
kW-mo/yr
- - - - - - - - -
02 4.123: Reduce defects by reducing product tipping $16,683 $96,069 - - - - - - - - - $16,683 -
03 2.7491: Insulate glazing, walls, ceilings, and roofs $812 $1,219 - - $812
-
MMBtu
- - - - - - - -
04 2.8227: Adjust / maintain fork lift trucks for most efficient operation $92,758 $115,000 - - - $216
-
MMBtu
- $92,542 - - - - -
05 4.664: Level three - install or modify control system with communication and nonlocal external information (i.e. weather foreca $57,690 $7,906 - - - - - $5,200 - - - $52,490 -
06 4.212: Adopt in-house material generation $36,181 $110,000 - - - - - - $36,181 - - - -
07 2.9114: Use solar heat to make electricty $37,019 $162,415 $37,019
324,165
kWh
- - - - - - - - - -
08 2.7447: Install vinyl strip / high speed / air curtain doors $24,539 $52,000 $24,398
213,639
kWh
$141
-
kW-mo/yr
- - - - - - - - -
09 4.132: Purchase new equipment to reduce material use / cost $252,286 $90,000 - - - - - - - $132,000 - - $120,286
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,737 $25,000 $4,429
38,785
kWh
$308
-
kW-mo/yr
- - - - - - - - -
11 3.3113: Use other methods for neutralization $13,133 $58,000 - - - - $3,133
-
Tgal
- - - $10,000 - -
TOTAL RECOMMENDED $535,979 $717,829 $65,972
577,693
kWh
$464
-
kW-mo/yr
$812
-
MMBtu
$216
-
MMBtu
$3,133
-
Tgal
$97,742 $36,181 $132,000 $10,000 $69,173 $120,286
TOTAL IMPLEMENTED - - - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs