Assessment Year | 2024 |
---|---|
Principal Product | Beer, Cider |
NAICS | 312120: Breweries |
SIC | 2082: Malt Beverages |
Sales Range | $1 M to 5M |
# of Employees | 15 |
Plant Area |
17,500
ft2
|
Annual Production | 492
Tgal
|
Production Hrs. Annual | 5,110
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $66,298 | 580,556 |
kWh
|
$0.11 | |
Electricity Demand | $7,248 | 1,252 |
kW-mo/yr
|
$5.79 | |
Electricity Fees | $5,995 | - |
|
- | |
Natural Gas | $31,410 | 2,834 |
MMBtu
|
$11.08 | |
LPG | $1,731 | 78 |
MMBtu
|
$22.09 | |
Other Gas | $15,266 | 1 |
MMBtu
|
$15,265.52 | |
Waste Disposal Costs | |||||
Water Usage | $7,000 | 2,820 |
Tgal
|
$2.48 | |
Water Disposal | $15,666 | 2,820 |
Tgal
|
$5.56 | |
Gaseous Waste | $57,096 | 143,890 |
lb
|
$0.40 | |
TOTAL YEARLY COSTS | $207,708 | ||||
RECOMMENDED SAVINGS* | $535,979 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $141 | $220 |
$126
1,104
kWh
|
$15
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
02 | 4.123: Reduce defects by reducing product tipping | $16,683 | $96,069 | - | - | - | - | - | - | - | - | - | $16,683 | - | |
03 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $812 | $1,219 | - | - |
$812
-
MMBtu
|
- | - | - | - | - | - | - | - | |
04 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $92,758 | $115,000 | - | - | - |
$216
-
MMBtu
|
- | $92,542 | - | - | - | - | - | |
05 | 4.664: Level three - install or modify control system with communication and nonlocal external information (i.e. weather foreca | $57,690 | $7,906 | - | - | - | - | - | $5,200 | - | - | - | $52,490 | - | |
06 | 4.212: Adopt in-house material generation | $36,181 | $110,000 | - | - | - | - | - | - | $36,181 | - | - | - | - | |
07 | 2.9114: Use solar heat to make electricty | $37,019 | $162,415 |
$37,019
324,165
kWh
|
- | - | - | - | - | - | - | - | - | - | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $24,539 | $52,000 |
$24,398
213,639
kWh
|
$141
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
09 | 4.132: Purchase new equipment to reduce material use / cost | $252,286 | $90,000 | - | - | - | - | - | - | - | $132,000 | - | - | $120,286 | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,737 | $25,000 |
$4,429
38,785
kWh
|
$308
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
11 | 3.3113: Use other methods for neutralization | $13,133 | $58,000 | - | - | - | - |
$3,133
-
Tgal
|
- | - | - | $10,000 | - | - | |
TOTAL RECOMMENDED | $535,979 | $717,829 |
$65,972
577,693
kWh
|
$464
-
kW-mo/yr
|
$812
-
MMBtu
|
$216
-
MMBtu
|
$3,133
-
Tgal
|
$97,742 | $36,181 | $132,000 | $10,000 | $69,173 | $120,286 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs