Assessment Year | 2024 |
---|---|
Principal Product | Galvanized steel products |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
26,800
ft2
|
Annual Production | 53,413,636
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $22,791 | 612,813 |
kWh
|
$0.037 | |
Electricity Demand | $17,938 | 1,890 |
kW-mo/yr
|
$9.49 | |
Electricity Fees | $3,169 | - |
|
- | |
Natural Gas | $173,059 | 88,919 |
MMBtu
|
$1.95 | |
Waste Disposal Costs | |||||
Water Usage | $12,124 | 681 |
Tgal
|
$17.80 | |
TOTAL YEARLY COSTS | $229,080 | ||||
RECOMMENDED SAVINGS* | $43,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $131 | $414 |
$60
1,615
kWh
|
$71
-
kW-mo/yr
|
- | - | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $249 | - |
$249
6,683
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,040 | $1,056 |
$698
18,754
kWh
|
$342
-
kW-mo/yr
|
- | - | - | |
04 | 2.4322: Use or replace with energy efficient substitutes | $4,552 | $19,950 |
$2,666
71,679
kWh
|
$1,886
-
kW-mo/yr
|
- | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,461 | $1,258 | - | - | - |
$3,461
-
MMBtu
|
- | |
06 | 4.812: Apply for investment incentives | $3,553 | $5,000 | - | - | $3,553 | - | - | |
07 | 4.132: Purchase new equipment to reduce material use / cost | $30,115 | $80,000 | - | - | - |
$865
-
MMBtu
|
$29,250 | |
TOTAL RECOMMENDED | $43,100 | $107,678 |
$3,673
98,731
kWh
|
$2,299
-
kW-mo/yr
|
$3,553 |
$4,326
-
MMBtu
|
$29,250 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs