ITAC Assessment: OR0784
ITAC logo
ITAC Assessment: OR0784
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Effluent
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $10
M
to 50
M
# of Employees 89
Plant Area 3,571,920
ft2
Annual Production 11,977
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $654,204 12,510,000
kWh
Electricity Demand $162,651 23,904
kW-mo/yr
Electricity Fees $34,407 -
Natural Gas $249,316 31,306
MMBtu
Waste Disposal Costs
Water Usage $41,336 10,383
Tgal
Other Liquid (non-haz) $502,113 218,310
gal
TOTAL YEARLY COSTS $1,644,027
RECOMMENDED SAVINGS* $408,659 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,041

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Primary Raw Material Savings Water Consumption Savings
01 3.3133: Use other waste concentration methods $61,484 $125,000 $61,484
1,175,820
kWh
- - - -
02 4.131: Modify process to reduce material use/cost $343,134 $700,000 $(-3,769.0)
(-72,085)
kWh
- $502,113
-
gal
$(-23,242.0) $(-131,968.0)
-
Tgal
03 2.9114: Use solar heat to make electricty $4,041 $12,113 $2,909
54,566
kWh
$1,132
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $408,659 $837,113 $60,624
1,158,301
kWh
$1,132
-
kW-mo/yr
$502,113
-
gal
$(-23,242.0) $(-131,968.0)
-
Tgal
TOTAL IMPLEMENTED $4,041 $12,113 $2,909
54,566
kWh
$1,132
-
kW-mo/yr
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs