Assessment Year | 2024 |
---|---|
Principal Product | Effluent |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 89 |
Plant Area |
3,571,920
ft2
|
Annual Production | 11,977
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $654,204 | 12,510,000 |
kWh
|
$0.052 | |
Electricity Demand | $162,651 | 23,904 |
kW-mo/yr
|
$6.80 | |
Electricity Fees | $34,407 | - |
|
- | |
Natural Gas | $249,316 | 31,306 |
MMBtu
|
$7.96 | |
Waste Disposal Costs | |||||
Water Usage | $41,336 | 10,383 |
Tgal
|
$3.98 | |
Other Liquid (non-haz) | $502,113 | 218,310 |
gal
|
$2.30 | |
TOTAL YEARLY COSTS | $1,644,027 | ||||
RECOMMENDED SAVINGS* | $408,659 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $4,041 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Primary Raw Material Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.3133: Use other waste concentration methods | $61,484 | $125,000 |
$61,484
1,175,820
kWh
|
- | - | - | - | |
02 | 4.131: Modify process to reduce material use/cost | $343,134 | $700,000 |
$(-3,769.0)
(-72,085)
kWh
|
- |
$502,113
-
gal
|
$(-23,242.0) |
$(-131,968.0)
-
Tgal
|
|
03 | 2.9114: Use solar heat to make electricty | $4,041 | $12,113 |
$2,909
54,566
kWh
|
$1,132
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $408,659 | $837,113 |
$60,624
1,158,301
kWh
|
$1,132
-
kW-mo/yr
|
$502,113
-
gal
|
$(-23,242.0) |
$(-131,968.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,041 | $12,113 |
$2,909
54,566
kWh
|
$1,132
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs