| Assessment Year | 2024 |
|---|---|
| Principal Product | Effluent |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 89 |
| Plant Area |
3,571,920
ft2
|
| Annual Production | 11,977
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $654,204 | 12,510,000 |
kWh
|
$0.052 | |
| Electricity Demand | $162,651 | 23,904 |
kW-mo/yr
|
$6.80 | |
| Electricity Fees | $34,407 | - |
|
- | |
| Natural Gas | $249,316 | 31,306 |
MMBtu
|
$7.96 | |
| Waste Disposal Costs | |||||
| Water Usage | $41,336 | 10,383 |
Tgal
|
$3.98 | |
| Other Liquid (non-haz) | $502,113 | 218,310 |
gal
|
$2.30 | |
| TOTAL YEARLY COSTS | $1,644,027 | ||||
| RECOMMENDED SAVINGS* | $408,659 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $4,041 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Primary Raw Material Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.3133: Use other waste concentration methods | $61,484 | $125,000 |
$61,484
1,175,820
kWh
|
- | - | - | - | |
| 02 | 4.131: Modify process to reduce material use/cost | $343,134 | $700,000 |
$(-3,769.0)
(-72,085)
kWh
|
- |
$502,113
-
gal
|
$(-23,242.0) |
$(-131,968.0)
-
Tgal
|
|
| 03 | 2.9114: Use solar heat to make electricty | $4,041 | $12,113 |
$2,909
54,566
kWh
|
$1,132
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $408,659 | $837,113 |
$60,624
1,158,301
kWh
|
$1,132
-
kW-mo/yr
|
$502,113
-
gal
|
$(-23,242.0) |
$(-131,968.0)
-
Tgal
|
||
| TOTAL IMPLEMENTED | $4,041 | $12,113 |
$2,909
54,566
kWh
|
$1,132
-
kW-mo/yr
|
- | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs