Assessment Year | 2021 |
---|---|
Principal Product | small metal couplings |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3429: Hardware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 336 |
Plant Area |
125,000
ft2
|
Annual Production | 63,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $688,819 | 9,560,784 |
kWh
|
$0.072 | |
Natural Gas | $79,533 | 38,512 |
MMBtu
|
$2.07 | |
Waste Disposal Costs | |||||
Water Usage | $127,681 | 13,562 |
Tgal
|
$9.41 | |
TOTAL YEARLY COSTS | $896,033 | ||||
RECOMMENDED SAVINGS* | $168,441 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $924 | $1,200 |
$924
12,960
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $669 | $200 |
$669
9,374
kWh
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $2,596 | $6,400 |
$2,596
37,235
kWh
|
- | - | |
04 | 2.6127: Maintain air filters by cleaning or replacement | $1,669 | $288 |
$1,669
21,402
kWh
|
- | - | |
05 | 2.2441: Preheat boiler makeup water with waste process heat | $3,506 | $8,000 | - |
$3,506
-
MMBtu
|
- | |
06 | 4.132: Purchase new equipment to reduce material use / cost | $100,865 | $197,145 |
$(-2,506.0)
(-35,100)
kWh
|
- | $103,371 | |
07 | 4.132: Purchase new equipment to reduce material use / cost | $57,876 | $199,418 |
$(-2,034.0)
(-29,700)
kWh
|
- | $59,910 | |
08 | 2.7135: Install occupancy sensors | $336 | $360 |
$336
4,717
kWh
|
- | - | |
TOTAL RECOMMENDED | $168,441 | $413,011 |
$1,654
20,888
kWh
|
$3,506
-
MMBtu
|
$163,281 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs