Assessment Year | 2024 |
---|---|
Principal Product | Dimensional Lumber |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $5 M to 10M |
# of Employees | 25 |
Plant Area |
174,240
ft2
|
Annual Production | 2,562
thousand feet
|
Production Hrs. Annual | 2,168
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $88,332 | 1,289,540 |
kWh
|
$0.068 |
Electricity Demand | $63,326 | 8,387 |
kW-mo/yr
|
$7.55 |
Electricity Fees | $26,624 | - |
|
- |
TOTAL YEARLY COSTS | $178,282 | |||
RECOMMENDED SAVINGS* | $70,061 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.131: Modify process to reduce material use/cost | $1,848 | - | - | - | - | $1,848 | |
02 | 2.4313: Provide proper maintenance of motor driven equipment | $42,000 | $50,000 |
$42,000
629,025
kWh
|
- | - | - | |
03 | 2.3212: Optimize plant power factor | $15,143 | $44,093 | - | - | $15,143 | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,400 | $6,763 |
$1,564
22,828
kWh
|
$836
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,786 | $5,438 |
$1,216
17,755
kWh
|
$570
-
kW-mo/yr
|
- | - | |
06 | 2.9114: Use solar heat to make electricty | $6,884 | $92,435 |
$4,731
69,059
kWh
|
$2,153
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $70,061 | $198,729 |
$49,511
738,667
kWh
|
$3,559
-
kW-mo/yr
|
$15,143 | $1,848 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs