ITAC Assessment: SF0619
ITAC logo
ITAC Assessment: SF0619
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Fluid Milks
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $100
M
to 500
M
# of Employees 150
Plant Area 150,000
ft2
Annual Production 14,500,000
units
Production Hrs. Annual 8,400
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $882,039 12,598,980
kWh
Electricity Demand $589,421 30,957
kW-mo/yr
Electricity Fees $121,981 -
Natural Gas $1,494,906 198,921
MMBtu
Waste Disposal Costs
Water Usage $532,771 185,419
Tgal
Water Disposal $1,039,953 38,610
Tgal
TOTAL YEARLY COSTS $4,661,071
RECOMMENDED SAVINGS* $744,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings
01 2.2135: Repair and eliminate steam leaks $4,612 - - - - $5,314
-
MMBtu
$178
-
Tgal
- $(-880.0) - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $5,589 $220 $4,074
55,635
kWh
$1,515
-
kW-mo/yr
- - - - - - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $241 - - - $241 - - - - - -
04 3.4156: Use flow control valves on equipment to optimize water use $39,174 $7,044 - - - - $3,775
-
Tgal
$35,399
-
Tgal
- - -
05 2.2163: Use minimum steam operating pressure $7,106 $2,700 $789
9,905
kWh
- - $6,317
-
MMBtu
- - - - -
06 3.4111: Use closed cycle process to minimize waste water production $90,155 $37,058 - - - - $8,688
-
Tgal
$81,467
-
Tgal
- - -
07 2.2111: Install steam trap $531,211 $270,719 - - - $137,992
-
MMBtu
$40,197
-
Tgal
$353,022
-
Tgal
- - -
08 2.4239: Eliminate or reduce compressed air usage $6,389 $4,926 $6,389
80,167
kWh
- - - - - - - -
09 2.2511: Insulate bare equipment $2,201 $2,875 - - - $2,201
-
MMBtu
- - - - -
10 2.7135: Install occupancy sensors $292 $785 $145
1,687
kWh
- - - - - $58 $89 -
11 4.132: Purchase new equipment to reduce material use / cost $52,391 $160,125 $(-7,479.0)
(-93,845)
kWh
- - - - - - - $59,870
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,993 $16,268 $3,723
46,717
kWh
$1,270
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $744,354 $502,720 $7,641
100,266
kWh
$2,785
-
kW-mo/yr
$241 $151,824
-
MMBtu
$52,838
-
Tgal
$469,888
-
Tgal
$(-822.0) $89 $59,870
TOTAL IMPLEMENTED - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs