Assessment Year | 2024 |
---|---|
Principal Product | Fluid Milks |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $100 M to 500M |
# of Employees | 150 |
Plant Area |
150,000
ft2
|
Annual Production | 14,500,000
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $882,039 | 12,598,980 |
kWh
|
$0.070 | |
Electricity Demand | $589,421 | 30,957 |
kW-mo/yr
|
$19.04 | |
Electricity Fees | $121,981 | - |
|
- | |
Natural Gas | $1,494,906 | 198,921 |
MMBtu
|
$7.52 | |
Waste Disposal Costs | |||||
Water Usage | $532,771 | 185,419 |
Tgal
|
$2.87 | |
Water Disposal | $1,039,953 | 38,610 |
Tgal
|
$26.94 | |
TOTAL YEARLY COSTS | $4,661,071 | ||||
RECOMMENDED SAVINGS* | $744,354 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $4,612 | - | - | - | - |
$5,314
-
MMBtu
|
$178
-
Tgal
|
- | $(-880.0) | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,589 | $220 |
$4,074
55,635
kWh
|
$1,515
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $241 | - | - | - | $241 | - | - | - | - | - | - | |
04 | 3.4156: Use flow control valves on equipment to optimize water use | $39,174 | $7,044 | - | - | - | - |
$3,775
-
Tgal
|
$35,399
-
Tgal
|
- | - | - | |
05 | 2.2163: Use minimum steam operating pressure | $7,106 | $2,700 |
$789
9,905
kWh
|
- | - |
$6,317
-
MMBtu
|
- | - | - | - | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $90,155 | $37,058 | - | - | - | - |
$8,688
-
Tgal
|
$81,467
-
Tgal
|
- | - | - | |
07 | 2.2111: Install steam trap | $531,211 | $270,719 | - | - | - |
$137,992
-
MMBtu
|
$40,197
-
Tgal
|
$353,022
-
Tgal
|
- | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $6,389 | $4,926 |
$6,389
80,167
kWh
|
- | - | - | - | - | - | - | - | |
09 | 2.2511: Insulate bare equipment | $2,201 | $2,875 | - | - | - |
$2,201
-
MMBtu
|
- | - | - | - | - | |
10 | 2.7135: Install occupancy sensors | $292 | $785 |
$145
1,687
kWh
|
- | - | - | - | - | $58 | $89 | - | |
11 | 4.132: Purchase new equipment to reduce material use / cost | $52,391 | $160,125 |
$(-7,479.0)
(-93,845)
kWh
|
- | - | - | - | - | - | - | $59,870 | |
12 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,993 | $16,268 |
$3,723
46,717
kWh
|
$1,270
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $744,354 | $502,720 |
$7,641
100,266
kWh
|
$2,785
-
kW-mo/yr
|
$241 |
$151,824
-
MMBtu
|
$52,838
-
Tgal
|
$469,888
-
Tgal
|
$(-822.0) | $89 | $59,870 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs