10,658
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
UD1115 #03 Y:2025 | 03 | 2025 | Meter recycled water (to reduce sewer charges) | $1,016 | $760 |
n/a
|
UW2508 #04 Y:2025 | 04 | 2025 | Install dedicated mixing equip to optimize reuse of used rinseate & to preclude the need for inter-run cleaning | $116,528 | $582,640 |
n/a
|
UW2507 #06 Y:2025 | 06 | 2025 | Use less toxic and volatile solvent substitutes | $124,957 | $342,000 |
n/a
|
UF0632 #11 Y:2025 | 11 | 2025 | Use reverse osmosis to concentrate material | $3,839 | $3,079 |
n/a
|
LS2513 #01 Y:2025 | 01 | 2025 | Increase amount of waste recovered for resale | $12,200 | - |
n/a
|
WV0682 #02 Y:2025 | 02 | 2025 | Minimize water usage | $71,374 | $60,060 |
n/a
|
MS0449 #06 Y:2025 | 06 | 2025 | Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $21,369 | $10,437 |
n/a
|
MS0449 #05 Y:2025 | 05 | 2025 | Recover and reuse waste material | $24,000 | $14,060 |
n/a
|
TT0331 #02 Y:2025 | 02 | 2025 | Minimize water usage | $1,508 | $400 |
n/a
|
MZ0377 #07 Y:2025 | 07 | 2025 | Meter recycled water (to reduce sewer charges) | $31,698 | $9,040 |
n/a
|
DL0259 #01 Y:2025 | 01 | 2025 | Change procedures / equipment / operating conditions | $45,458 | $19,000 |
n/a
|
UU0271 #05 Y:2025 | 05 | 2025 | Eliminate leaks in water lines and valves | $771 | $5,877 |
n/a
|
UU0271 #04 Y:2025 | 04 | 2025 | Minimize water usage | $3,231 | $23,282 |
n/a
|
UD1111 #05 Y:2025 | 05 | 2025 | Meter recycled water (to reduce sewer charges) | $1,836 | $2,500 |
n/a
|
UD1111 #01 Y:2025 | 01 | 2025 | Use flow control valves on equipment to optimize water use | $38,544 | $2,352 |
n/a
|
SD0672 #10 Y:2025 | 10 | 2025 | Replace water cooling on processes with air cooling | $43,311 | $4,700 |
n/a
|
LE0599 #06 Y:2025 | 06 | 2025 | Use closed cycle process to minimize waste water production | $98,974 | $65,000 |
n/a
|
TT0328 #05 Y:2025 | 05 | 2025 | Replace city water with recycled water via cooling tower | $52,760 | $41,250 |
n/a
|
TT0328 #01 Y:2025 | 01 | 2025 | Reduce or eliminate waste | $296,352 | $1,200,000 |
n/a
|
LE0598 #03 Y:2025 | 03 | 2025 | Convert to robotic painting | $218,856 | $362,095 |
n/a
|