| Assessment Year | 2025 |
|---|---|
| Principal Product | Wood/gas/pellet stove |
| NAICS | 335221: Household Cooking Appliance Manufacturing |
| SIC | 3631: Household Cooking Equipment |
| Sales Range | $500 k to 1M |
| # of Employees | 150 |
| Plant Area |
110,000
ft2
|
| Annual Production | 39,000
units
|
| Production Hrs. Annual | 5,100
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $247,385 | 2,345,250 |
kWh
|
$0.11 |
| Electricity Demand | $35,219 | 8,838 |
kW-mo/yr
|
$3.98 |
| Electricity Fees | $720 | - |
|
- |
| LPG | $75,476 | 2,993 |
MMBtu
|
$25.22 |
| TOTAL YEARLY COSTS | $358,800 | |||
| RECOMMENDED SAVINGS* | $52,690 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $5,489 | $720 |
$1,128
10,740
kWh
|
$4,361
-
MMBtu
|
|
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $4,374 | - |
$996
9,482
kWh
|
$3,378
-
MMBtu
|
|
| 03 | 3.1191: Change procedures / equipment / operating conditions | $9,021 | $7,950 |
$1,508
14,363
kWh
|
$7,513
-
MMBtu
|
|
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,337 | $90,000 |
$15,337
146,062
kWh
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,186 | $16,400 |
$14,186
135,100
kWh
|
- | |
| 06 | 2.4323: Use optimum size and capacity equipment | $4,283 | $1,200 |
$4,283
40,786
kWh
|
- | |
| TOTAL RECOMMENDED | $52,690 | $116,270 |
$37,438
356,533
kWh
|
$15,252
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs