Assessment Year | 1989 |
---|---|
Principal Product | WOMEN'S SPORTSWEAR |
NAICS |
n/a
|
SIC | 2339: Women's, Misses', and Juniors' Outerwear, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 320 |
Plant Area |
n/a
|
Annual Production | 2,300,000
pieces
|
Production Hrs. Annual | 4,320
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $146,001 | 2,731,536 |
kWh
|
$0.053 |
Natural Gas | $35,284 | 7,708 |
MMBtu
|
$4.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $1,826 | $622 | - |
$1,826
-
MMBtu
|
- | |
02 | 2.2135: Repair and eliminate steam leaks | $1,822 | $360 | - |
$1,822
-
MMBtu
|
- | |
03 | 2.7123: Keep lamps and reflectors clean | $4,940 | $11,550 |
$4,836
91,149
kWh
|
- | $104 | |
04 | 2.2163: Use minimum steam operating pressure | $511 | - | - |
$511
-
MMBtu
|
- | |
05 | 2.2511: Insulate bare equipment | $474 | $442 | - |
$474
-
MMBtu
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $354 | $300 | - |
$354
-
MMBtu
|
- | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,387 | - |
$1,387
17,878
kWh
|
- | - | |
08 | 2.2122: Install / repair insulation on condensate lines | $166 | $60 | - |
$166
-
MMBtu
|
- | |
09 | 2.2531: Re-size charging openings or add movable cover or door | $79 | - | - |
$79
-
MMBtu
|
- | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $326 | $84 |
$326
6,155
kWh
|
- | - | |
TOTAL RECOMMENDED | $11,885 | $13,418 |
$6,549
115,182
kWh
|
$5,232
-
MMBtu
|
$104 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs