ITAC Assessment: MU0072
ITAC logo
ITAC Assessment: MU0072
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Copper Carbonate
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2491: Wood Preserving
Sales Range less than $500
k
# of Employees 60
Plant Area 40,000
ft2
Annual Production 65,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $708,241 8,283,705
kWh
Electricity Demand $210,900 32,985
kW-mo/yr
Electricity Fees $29,110 -
Natural Gas $1,541,831 313,795
MMBtu
Other Gas $337,590 1
MMBtu
TOTAL YEARLY COSTS $2,827,672
RECOMMENDED SAVINGS* $165,491 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.2424: Use heat in flue gases to preheat products or materials $161,393 $126,876 - - $161,393
-
MMBtu
-
02 2.7135: Install occupancy sensors $1,481 $960 $1,290
15,177
kWh
$191
-
kW-mo/yr
- -
03 2.2437: Recover waste heat from equipment $38 $271 - - $38
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,343 $9,811 $1,169
13,758
kWh
$173
-
kW-mo/yr
- -
05 2.7134: Use photocell controls $138 $404 $89
1,052
kWh
$49
-
kW-mo/yr
- -
06 2.7221: Lower temperature during the winter season and vice-versa $228 - $105
1,235
kWh
$123
-
kW-mo/yr
- -
07 2.7221: Lower temperature during the winter season and vice-versa $231 - $160
1,882
kWh
$71
-
kW-mo/yr
- -
08 3.5315: Lease / purchase baler; sell cardboard to recycler $640 - - - - $640
TOTAL RECOMMENDED $165,491 $138,322 $2,814
33,103
kWh
$607
-
kW-mo/yr
$161,431
-
MMBtu
$640
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs