| Assessment Year | 2025 |
|---|---|
| Principal Product | matress |
| NAICS | 337910: Mattress Manufacturing |
| SIC | 2515: Mattresses, Foundations, and Convertible Beds |
| Sales Range | $10 M to 50M |
| # of Employees | 56 |
| Plant Area |
212,975
ft2
|
| Annual Production | 307,858,723
units
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $142,641 | 1,091,231 |
kWh
|
$0.13 | |
| Electricity Demand | $41,174 | 6,015 |
kW-mo/yr
|
$6.85 | |
| Electricity Fees | $5,871 | - |
|
- | |
| Natural Gas | $22,336 | 7,999 |
MMBtu
|
$2.79 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,467 | 497 |
Tgal
|
$2.95 | |
| Water Disposal | $1,758 | 497 |
Tgal
|
$3.54 | |
| TOTAL YEARLY COSTS | $215,247 | ||||
| RECOMMENDED SAVINGS* | $34,416 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,515 | $7,035 |
$23,798
183,062
kWh
|
$1,717
-
kW-mo/yr
|
- | - | |
| 02 | 2.3212: Optimize plant power factor | $2,927 | $3,700 | - | - | $2,927 | - | |
| 03 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,016 | $760 | - | - | - |
$1,016
-
Tgal
|
|
| 04 | 2.2511: Insulate bare equipment | $892 | $1,267 |
$892
6,828
kWh
|
- | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,587 | $5,423 |
$2,139
16,369
kWh
|
$448
-
kW-mo/yr
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $1,479 | $1,015 |
$1,219
9,327
kWh
|
$260
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $34,416 | $19,200 |
$28,048
215,586
kWh
|
$2,425
-
kW-mo/yr
|
$2,927 |
$1,016
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs