ITAC Assessment: SU0581
ITAC logo
ITAC Assessment: SU0581
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Baked Goods
NAICS 311811: Retail Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 88,843
ft2
Annual Production 2,400,000
units
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,769 7,920,137
kWh
Electricity Demand $96,250 7,393
kW-mo/yr
Electricity Fees $3,639 -
Natural Gas $245,508 39,693
MMBtu
Other Gas $539 39,693
MMBtu
TOTAL YEARLY COSTS $566,705
RECOMMENDED SAVINGS* $13,865 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.3132: Recharge batteries on during off-peak demand periods $990 - - $990
-
kW-mo/yr
- -
02 2.7122: Disconnect ballasts $331 - $174
6,228
kWh
$156
-
kW-mo/yr
- -
03 2.4239: Eliminate or reduce compressed air usage $1,466 - $1,466
52,362
kWh
- - -
04 2.7224: Reduce space conditioning during non-working hours $1,336 - - - $1,336
-
MMBtu
-
05 2.4322: Use or replace with energy efficient substitutes $697 $38 $235
8,400
kWh
$684
-
kW-mo/yr
$(-221.6)
-
MMBtu
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,579 $1,648 $1,576
56,278
kWh
$1,003
-
kW-mo/yr
- -
07 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $1,877 $1,220 $1,877
67,024
kWh
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $149 $172 $25
899
kWh
$58
-
kW-mo/yr
- $66
09 2.2437: Recover waste heat from equipment $4,318 $15,784 - - $4,318
-
MMBtu
-
10 2.7135: Install occupancy sensors $123 $769 $123
4,380
kWh
- - -
TOTAL RECOMMENDED $13,865 $19,630 $5,476
195,570
kWh
$2,890
-
kW-mo/yr
$5,432
-
MMBtu
$66
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs