Assessment Year | 2025 |
---|---|
Principal Product | Cold-formed steel building products |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
307,420
ft2
|
Annual Production | 7,221,082
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $187,464 | 5,837,184 |
kWh
|
$0.032 | |
Electricity Demand | $90,976 | 11,249 |
kW-mo/yr
|
$8.09 | |
Electricity Fees | $42,349 | - |
|
- | |
Natural Gas | $125,579 | 33,933 |
MMBtu
|
$3.70 | |
Waste Disposal Costs | |||||
Water Usage | $10,000 | 40 |
Tgal
|
$250.00 | |
TOTAL YEARLY COSTS | $456,368 | ||||
RECOMMENDED SAVINGS* | $63,334 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $18,599 | $24,000 |
$10,768
335,462
kWh
|
$7,831
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,123 | $9,580 |
$5,706
177,772
kWh
|
$4,417
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $9,267 | $13,716 |
$5,287
164,698
kWh
|
$3,980
-
kW-mo/yr
|
- | - | - | |
04 | 2.7241: Install outside air damper / economizer on hvac unit | $6,295 | $24,800 |
$3,828
119,251
kWh
|
$2,467
-
kW-mo/yr
|
- | - | - | |
05 | 2.4224: Upgrade controls on compressors | $5,215 | $5,557 |
$3,071
95,661
kWh
|
$2,144
-
kW-mo/yr
|
- | - | - | |
06 | 3.3131: Use evaporation to concentrate material | $4,913 | $21,336 | - | - |
$(-1,554.0)
-
MMBtu
|
$(-3,033.0) |
$9,500
-
Tgal
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,391 | $10,040 |
$2,466
76,820
kWh
|
$1,925
-
kW-mo/yr
|
- | - | - | |
08 | 2.4156: Establish a preventative maintenance program | $1,612 | $1,500 |
$1,412
43,991
kWh
|
$1,027
-
kW-mo/yr
|
- | $(-827.0) | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,242 | $743 |
$837
26,068
kWh
|
$405
-
kW-mo/yr
|
- | - | - | |
10 | 2.4151: Develop a repair/replace policy | $1,229 | $5,827 |
$953
29,694
kWh
|
$696
-
kW-mo/yr
|
- | $(-420.0) | - | |
11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $245 | $70 |
$164
5,099
kWh
|
$81
-
kW-mo/yr
|
- | - | - | |
12 | 2.4239: Eliminate or reduce compressed air usage | $203 | $673 |
$138
4,313
kWh
|
$65
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $63,334 | $117,842 |
$34,630
1,078,829
kWh
|
$25,038
-
kW-mo/yr
|
$(-1,554.0)
-
MMBtu
|
$(-4,280.0) |
$9,500
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs