Assessment Year | 2005 |
---|---|
Principal Product | Wooden Countertops |
NAICS | 337110: Wood Kitchen Cabinet and Countertop Manufacturing |
SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
35,000
ft2
|
Annual Production | 624,000
thousand feet
|
Production Hrs. Annual | 2,388
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $42,490 | 281,248 |
kWh
|
$0.15 |
Natural Gas | $2,231 | 203 |
MMBtu
|
$10.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,533 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,570 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $496 | - |
$496
4,330
kWh
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,557 | $11,268 |
$7,557
51,444
kWh
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $337 | $748 |
$337
2,295
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $474 | $1,638 |
$474
3,224
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $600 | $2,584 |
$600
4,083
kWh
|
- | |
06 | 2.4224: Upgrade controls on compressors | $2,069 | $15,913 |
$2,069
14,083
kWh
|
- | |
07 | 3.5218: Reuse / recycle/ sell rubber products | $1,800 | $250 | - |
$1,800
-
lb
|
|
08 | 3.5314: Use in-process recycling whenever possible | $1,200 | - | - |
$1,200
-
lb
|
|
TOTAL RECOMMENDED | $14,533 | $32,401 |
$11,533
79,459
kWh
|
$3,000
-
lb
|
||
TOTAL IMPLEMENTED | $4,570 | $4,472 |
$1,570
11,637
kWh
|
$3,000
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs