Assessment Year | 2025 |
---|---|
Principal Product | Metal Doors |
NAICS | 332321: Metal Window and Door Manufacturing |
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $100 M to 500M |
# of Employees | 120 |
Plant Area |
110,000
ft2
|
Annual Production | 1,200
units
|
Production Hrs. Annual | 6,051
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $2,179 | 45,396 |
kWh
|
$0.048 | |
Electricity Demand | $50,007 | 3,660 |
kW-mo/yr
|
$13.66 | |
Electricity Fees | $5,038 | - |
|
- | |
Natural Gas | $87,058 | 9,283 |
MMBtu
|
$9.38 | |
Other Gas | $6,856 | 1 |
MMBtu
|
$6,856.00 | |
Waste Disposal Costs | |||||
Water Usage | $999 | 181 |
Tgal
|
$5.53 | |
Other Liquid (non-haz) | $139 | 1 |
gal
|
$139.00 | |
TOTAL YEARLY COSTS | $152,276 | ||||
RECOMMENDED SAVINGS* | $66,549 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $45,419 | $54,600 |
$2,039
42,478
kWh
|
$1,151
-
kW-mo/yr
|
- | - | - | - | - | $42,229 | |
02 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $13,580 | $600 | - | - | - | - | - | - | $13,580 | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $5,745 | $2,300 | - | - | $4,580 | - |
$1,165
-
MMBtu
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $828 | $4,650 |
$828
17,257
kWh
|
- | - | - | - | - | - | - | |
05 | 2.2511: Insulate bare equipment | $566 | $655 | - | - | - |
$566
-
MMBtu
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $411 | $423 |
$45
944
kWh
|
$26
-
kW-mo/yr
|
- | - | - | $340 | - | - | |
TOTAL RECOMMENDED | $66,549 | $63,228 |
$2,912
60,679
kWh
|
$1,177
-
kW-mo/yr
|
$4,580 |
$566
-
MMBtu
|
$1,165
-
MMBtu
|
$340 | $13,580 | $42,229 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs