3,374
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
UF0630 #03 Y:2025 | 03 | 2025 | Use demand controller or load shedder | $12,224 | $8,907 |
n/a
|
SJ0035 #06 Y:2025 | 06 | 2025 | Use battery storage for demand control | $106,498 | $186,900 |
n/a
|
MI0458 #01 Y:2025 | 01 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $4,021 | - |
n/a
|
UL2504 #07 Y:2025 | 07 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $4,512 | - |
n/a
|
SD0673 #02 Y:2025 | 02 | 2025 | Use battery storage for demand control | $652,079 | $20,176 |
n/a
|
IC0326 #09 Y:2025 | 09 | 2025 | Recharge batteries on during off-peak demand periods | $941 | - |
n/a
|
IC0326 #06 Y:2025 | 06 | 2025 | Use demand controller or load shedder | $657 | $3,632 |
n/a
|
UF0629 #02 Y:2025 | 02 | 2025 | Use demand controller or load shedder | $14,163 | $14,913 |
n/a
|
SU0572 #03 Y:2025 | 03 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $2,576 | - |
n/a
|
SU0571 #03 Y:2025 | 03 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $8,170 | - |
n/a
|
SD0672 #07 Y:2025 | 07 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $30,634 | - |
n/a
|
SD0672 #02 Y:2025 | 02 | 2025 | Use battery storage for demand control | $11,678 | $2,631 |
n/a
|
MU0065 #03 Y:2025 | 03 | 2025 | Recharge batteries on during off-peak demand periods | $5,105 | $2,070 |
n/a
|
SU0568 #02 Y:2025 | 02 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $6,415 | - |
n/a
|
SD0671 #03 Y:2025 | 03 | 2025 | Recharge batteries on during off-peak demand periods | $3,996 | - |
n/a
|
SD0671 #02 Y:2025 | 02 | 2025 | Use battery storage for demand control | $2,541 | $1,352 |
n/a
|
MU0064 #04 Y:2025 | 04 | 2025 | Recharge batteries on during off-peak demand periods | $21,996 | $361 |
n/a
|
UF0628 #02 Y:2025 | 02 | 2025 | Use demand controller or load shedder | $43,459 | $43,906 |
n/a
|
SU0567 #03 Y:2025 | 03 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $5,769 | - |
n/a
|
AS0606 #01 Y:2025 | 01 | 2025 | Use battery storage for demand control | $3,172 | $6,000 |
n/a
|