Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,003

matching recommendations
$
$
ARC Demand management
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
CM1013 #02 Y:2022 Reschedule plant operations or reduce load to avoid peaks $8,342 $3,480
IC0274 #03 Y:2022 Use power during off-peak periods $24,024 -
GT0963 #02 Y:2022 Recharge batteries on during off-peak demand periods $2,457 $400
CI0005 #10 Y:2022 Reschedule plant operations or reduce load to avoid peaks $323 -
CI0005 #06 Y:2022 Store heated/ cooled water for use during peak demand periods $2,348 $8,100
GT0962 #01 Y:2022 Recharge batteries on during off-peak demand periods $5,691 $200
AM0867 #05 Y:2022 Reschedule plant operations or reduce load to avoid peaks $34,000 $10,000
CI0003 #08 Y:2022 Recharge batteries on during off-peak demand periods $1,200 $500
CI0001 #04 Y:2022 Recharge batteries on during off-peak demand periods $2,151 $100
CW0124 #03 Y:2022 User battery storage for power quality issues $230,341 $287,555
KS2206 #01 Y:2022 Recharge batteries on during off-peak demand periods $8,106 -
CM1003 #04 Y:2022 Use demand controller or load shedder $227 -
CO0744 #05 Y:2022 Use fossil fuel powered generator during peak demand periods $210,000 $58,000
DL0209 #01 Y:2022 Reschedule plant operations or reduce load to avoid peaks $18,464 -
CM1004 #06 Y:2022 Use battery storage for demand control $36,190 $195,000
CM1004 #05 Y:2022 Make ice during off peak hours for cooling $10,340 $57,600
IP0159 #01 Y:2022 Recharge batteries on during off-peak demand periods $3,135 -
IP0158 #02 Y:2022 Reschedule plant operations or reduce load to avoid peaks $2,990 -
CW0123 #10 Y:2022 Use power during off-peak periods $1,949 -
AS0518 #06 Y:2022 Schedule routine maintenance during non-operating periods $391 $1,619