| Assessment Year | 2026 |
|---|---|
| Principal Product | Plastic caps/ plastic injection & compression molding |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 137 |
| Plant Area |
275,000
ft2
|
| Annual Production | 6,441,815,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $2,314,898 | 36,445,976 |
kWh
|
$0.064 | |
| Electricity Demand | $1,465,109 | 64,117 |
kW-mo/yr
|
$22.85 | |
| Electricity Fees | $254,234 | - |
|
- | |
| Natural Gas | $27,706 | 4,168 |
MMBtu
|
$6.65 | |
| Other Gas | $5,863 | 1 |
MMBtu
|
$5,863.41 | |
| Waste Disposal Costs | |||||
| Water Usage | $76,216 | 7,213 |
Tgal
|
$10.57 | |
| Water Disposal | $14,987 | 1,349 |
Tgal
|
$11.11 | |
| TOTAL YEARLY COSTS | $4,159,012 | ||||
| RECOMMENDED SAVINGS* | $185,622 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $9,710 | $17,820 |
$6,460
101,730
kWh
|
$3,250
-
kW-mo/yr
|
|
| 02 | 2.7135: Install occupancy sensors | $387 | $600 |
$200
3,145
kWh
|
$188
-
kW-mo/yr
|
|
| 03 | 2.3141: Use battery storage for demand control | $44,744 | $200,990 |
$(-618.7)
9,743
kWh
|
$45,363
-
kW-mo/yr
|
|
| 04 | 2.4239: Eliminate or reduce compressed air usage | $34,861 | $175,256 |
$19,459
306,442
kWh
|
$15,402
-
kW-mo/yr
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,025 | $9,461 |
$5,855
92,206
kWh
|
$1,170
-
kW-mo/yr
|
|
| 06 | 2.3132: Recharge batteries on during off-peak demand periods | $3,791 | - | - |
$3,791
-
kW-mo/yr
|
|
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $4,576 | $1,000 |
$3,863
60,840
kWh
|
$713
-
kW-mo/yr
|
|
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $80,528 | $87,635 |
$47,541
748,684
kWh
|
$32,986
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $185,622 | $492,763 |
$82,760
1,322,790
kWh
|
$102,862
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs