Assessment Year | 2001 |
---|---|
Principal Product | Compaction Machinery and Equipment |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 225 |
Plant Area |
210,000
ft2
|
Annual Production | 950
units
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $157,186 | 4,052,800 |
kWh
|
$0.039 |
Electricity Demand | $131,678 | 11,906 |
kW-mo/yr
|
$11.06 |
Electricity Fees | $8,172 | - |
|
- |
Natural Gas | $325,787 | 40,708 |
MMBtu
|
$8.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $234,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $182,901 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $68,706 | $29,000 | - | - |
$68,706
-
MMBtu
|
- | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $44,275 | $22,875 |
$(-726.0)
18,799
kWh
|
$(-326.0)
-
kW-mo/yr
|
$45,327
-
MMBtu
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,104 | $2,900 |
$2,396
61,766
kWh
|
$1,708
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7135: Install occupancy sensors | $2,922 | $1,875 |
$1,425
36,735
kWh
|
$1,497
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $1,570 | $2,970 |
$1,023
26,370
kWh
|
$547
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,368 | $2,660 |
$813
20,966
kWh
|
$580
-
kW-mo/yr
|
- | - | - | - | $(-25.0) | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,352 | $1,000 |
$778
20,059
kWh
|
$574
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $324 | $350 |
$129
3,329
kWh
|
$51
-
kW-mo/yr
|
- | - | - | - | $144 | |
09 | 3.2121: Convert to electrostatic powder coating | $42,843 | $150,000 | n/a | - | - |
$(-15,881.0)
-
MMBtu
|
$58,724
-
gal
|
- | - | - |
10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,710 | $7,000 | - | - | - | - |
$2,710
-
lb
|
- | - | |
11 | 3.5316: Contract a wood pallet recycling company | $700 | $180 | - | - | - | - | - | $700 | - | |
12 | 3.5217: Reuse / recycle/ sell paper products | $663 | $500 | - | - | - | - |
$663
-
lb
|
- | - | |
13 | 2.8113: Purchase gas directly from a contract gas supplier | $62,772 | $5,000 | - | - | - | - | - | $62,772 | - | |
TOTAL RECOMMENDED | $234,309 | $226,310 |
$5,838
188,024
kWh
|
$4,631
-
kW-mo/yr
|
$98,152
-
MMBtu
|
$58,724
-
gal
|
$3,373
-
lb
|
$63,472 | $119 | ||
TOTAL IMPLEMENTED | $182,901 | $63,785 |
$3,390
124,919
kWh
|
$2,587
-
kW-mo/yr
|
$114,033
-
MMBtu
|
- | - | $62,772 | $119 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs