| Assessment Year | 2026 |
|---|---|
| Principal Product | Cast and Machined Aluminum Components |
| NAICS | 331524: Aluminum Foundries (except Die-Casting) |
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
65,000
ft2
|
| Annual Production | 75,000
units
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $173,980 | 581,422 |
kWh
|
$0.30 |
| Electricity Demand | $69,654 | 2,923 |
kW-mo/yr
|
$23.83 |
| Natural Gas | $70,349 | 3,027 |
MMBtu
|
$23.24 |
| TOTAL YEARLY COSTS | $313,983 | |||
| RECOMMENDED SAVINGS* | $32,400 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $14,993 | - |
$12,562
42,015
kWh
|
$2,431
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,160 | - |
$2,911
9,734
kWh
|
$249
-
kW-mo/yr
|
- | |
| 03 | 2.2211: Use optimum temperature | $1,605 | - |
$1,021
2,623
kWh
|
$584
-
kW-mo/yr
|
- | |
| 04 | 2.3141: Use battery storage for demand control | $8,817 | - | - |
$8,817
-
kW-mo/yr
|
- | |
| 05 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,244 | - |
$1,244
4,160
kWh
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $109 | $183 | - | - |
$109
-
MMBtu
|
|
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,472 | $13,610 |
$2,010
6,722
kWh
|
$462
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $32,400 | $13,793 |
$19,748
65,254
kWh
|
$12,543
-
kW-mo/yr
|
$109
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs