6,873
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
KS2437 #09 Y:2024 | 09 | 2024 | Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $65,208 | $627,000 |
n/a
|
UD1101 #11 Y:2024 | 11 | 2024 | Optimize plant power factor | $1,101 | $4,400 |
n/a
|
MI0454 #01 Y:2024 | 01 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $2,818 | - |
n/a
|
TR0060 #02 Y:2024 | 02 | 2024 | Optimize plant power factor | $27,671 | $119,707 |
n/a
|
NL0104 #02 Y:2024 | 02 | 2024 | Recharge batteries on during off-peak demand periods | $3,070 | $450 |
n/a
|
UD1100 #06 Y:2024 | 06 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $3,587 | - |
n/a
|
UD1100 #05 Y:2024 | 05 | 2024 | Optimize plant power factor | $12,387 | $23,400 |
n/a
|
LE0588 #04 Y:2024 | 04 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $13,600 | $26,934 |
n/a
|
IP0203 #05 Y:2024 | 05 | 2024 | Use demand controller or load shedder | $64,223 | $20,000 |
n/a
|
UU0264 #03 Y:2024 | 03 | 2024 | Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $729,671 | $3,645,455 |
n/a
|
UC2417 #02 Y:2024 | 02 | 2024 | Optimize plant power factor | $2,644 | $9,173 |
n/a
|
UU0263 #09 Y:2024 | 09 | 2024 | Optimize plant power factor | $3,940 | $9,000 |
n/a
|
UD1099 #01 Y:2024 | 01 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $4,391 | - |
n/a
|
SJ0030 #02 Y:2024 | 02 | 2024 | Use battery storage for demand control | $18,627 | $195,217 |
n/a
|
SD0664 #02 Y:2024 | 02 | 2024 | Use battery storage for demand control | $82,562 | $4,772 |
n/a
|
MU0061 #01 Y:2024 | 01 | 2024 | Recharge batteries on during off-peak demand periods | $3,468 | $4,140 |
n/a
|
KS2435 #05 Y:2024 | 05 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $2,807 | - |
n/a
|
SU0565 #01 Y:2024 | 01 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $6,336 | - |
n/a
|
GT0990 #06 Y:2024 | 06 | 2024 | Optimize plant power factor | $2,014 | $8,907 |
n/a
|
UF0624 #03 Y:2024 | 03 | 2024 | Use battery storage for demand control | $11,217 | $21,658 |
n/a
|