matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| UD1141 #07 Y:2026 | 07 | 2026 | Optimize plant power factor | $78,726 | $82,652 |
n/a
|
| UC2607 #01 Y:2026 | 01 | 2026 | Optimize plant power factor | $732 | $2,589 |
n/a
|
| SU0598 #01 Y:2026 | 01 | 2026 | Reschedule plant operations or reduce load to avoid peaks | $1,443 | - |
n/a
|
| AS0617 #04 Y:2026 | 04 | 2026 | Use battery storage for demand control | $4,794 | $41,498 |
n/a
|
| MU0091 #04 Y:2026 | 04 | 2026 | Optimize plant power factor | $12,469 | $38,117 |
n/a
|
| SD0693 #09 Y:2026 | 09 | 2026 | Recharge batteries on during off-peak demand periods | $14,692 | - |
n/a
|
| SD0693 #03 Y:2026 | 03 | 2026 | Use battery storage for demand control | $172,708 | $85,941 |
n/a
|
| SU0597 #01 Y:2026 | 01 | 2026 | Reschedule plant operations or reduce load to avoid peaks | $7,979 | - |
n/a
|
| NT0068 #07 Y:2026 | 07 | 2026 | Optimize plant power factor | $7,455 | $7,713 |
n/a
|
| LE0616 #03 Y:2026 | 03 | 2026 | Reschedule plant operations or reduce load to avoid peaks | $2,401 | $2,000 |
n/a
|
| IC0347 #11 Y:2026 | 11 | 2026 | Recharge batteries on during off-peak demand periods | $333 | - |
n/a
|
| LE0614 #05 Y:2026 | 05 | 2026 | Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $163,280 | $340,548 |
n/a
|
| MZ1023 #03 Y:2026 | 03 | 2026 | Make ice during off peak hours for cooling | $8,543 | $33,000 |
n/a
|
| LE0612 #05 Y:2026 | 05 | 2026 | Use demand controller or load shedder | $138,433 | $318,698 |
n/a
|
| LE0612 #02 Y:2026 | 02 | 2026 | Use demand controller or load shedder | $106,148 | $20,000 |
n/a
|
| GT1008 #04 Y:2026 | 04 | 2026 | Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $1,225,825 | $6,037,500 |
n/a
|
| UU0304 #02 Y:2026 | 02 | 2026 | Use battery storage for demand control | $5,300 | $5,300 |
n/a
|
| SD0692 #01 Y:2026 | 01 | 2026 | Use battery storage for demand control | $258,060 | $497,690 |
n/a
|
| CI0083 #05 Y:2026 | 05 | 2026 | Recharge batteries on during off-peak demand periods | $10,068 | $450 |
n/a
|
| UD1139 #06 Y:2026 | 06 | 2026 | Optimize plant power factor | $7,031 | $18,291 |
n/a
|