ITAC Assessment: TT0336
ITAC logo
ITAC Assessment: TT0336
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Applied Coatings and Repair of Industrial Machine Parts
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 18
Plant Area 25,000
ft2
Annual Production 32,919
units
Production Hrs. Annual 2,040
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,891 1,088,930
kWh
Electricity Demand $56,441 4,468
kW-mo/yr
Electricity Fees $2,834 -
Natural Gas $13,474 983
MMBtu
Other Gas $11,270 151
MMBtu
Waste Disposal Costs
Water Usage $3,356 293
Tgal
Water Disposal $4,764 293
Tgal
TOTAL YEARLY COSTS $184,030
RECOMMENDED SAVINGS* $68,459 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings
01 2.2312: Minimize non-essential material in heat treatment process $21,145 $30,000 $21,145
251,736
kWh
- - - -
02 2.3141: Use battery storage for demand control $19,703 $159,000 - $19,703
-
kW-mo/yr
- - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $13,640 $6,680 - $13,640
-
kW-mo/yr
- - -
04 2.1331: Burn a less expensive grade of fuel $6,724 $40,000 $(-1,645.1)
(-19,584)
kWh
- - $(-2,900.9)
-
MMBtu
$11,270
-
MMBtu
05 2.3212: Optimize plant power factor $2,201 $5,250 - - $2,201 - -
06 2.6231: Utilize controls to operate equipment only when needed $1,830 $500 $1,830
21,787
kWh
- - - -
07 2.4239: Eliminate or reduce compressed air usage $1,078 $400 $1,078
12,828
kWh
- - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $572 $60 $572
6,804
kWh
- - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $551 $375 $551
6,558
kWh
- - - -
10 2.6231: Utilize controls to operate equipment only when needed $507 $100 $507
6,039
kWh
- - - -
11 2.7135: Install occupancy sensors $355 $1,600 $355
4,227
kWh
- - - -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $153 $255 $153
1,826
kWh
- - - -
TOTAL RECOMMENDED $68,459 $244,220 $24,546
292,221
kWh
$33,343
-
kW-mo/yr
$2,201 $(-2,900.9)
-
MMBtu
$11,270
-
MMBtu
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs