Assessment Year | 2014 |
---|---|
Principal Product | Pastries |
NAICS | 311821: Cookie and Cracker Manufacturing |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
300,000
ft2
|
Annual Production | 150,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $669,829 | 16,950,983 |
kWh
|
$0.040 |
Electricity Demand | $292,679 | 33,082 |
kW-mo/yr
|
$8.85 |
Electricity Fees | $126,305 | - |
|
- |
Natural Gas | $709,899 | 88,479 |
MMBtu
|
$8.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $163,055 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $155,509 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $84,218 | $192,800 | - | - | - |
$84,218
-
MMBtu
|
- | |
02 | 2.2442: Preheat combustion air with waste heat | $20,868 | $60,000 | - | - | - |
$20,868
-
MMBtu
|
- | |
03 | 2.1224: Replace boiler | $18,647 | $49,610 | - | - | - |
$18,647
-
MMBtu
|
- | |
04 | 2.2511: Insulate bare equipment | $930 | $1,845 | - | - | - |
$930
-
MMBtu
|
- | |
05 | 2.4224: Upgrade controls on compressors | $13,621 | $15,000 |
$13,621
340,514
kWh
|
- | - | - | - | |
06 | 2.3212: Optimize plant power factor | $7,546 | $34,475 | - | - | $7,546 | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $2,190 | - |
$1,680
42,000
kWh
|
$510
-
kW-mo/yr
|
- | - | - | |
08 | 2.7131: Add area lighting switches | $1,572 | $620 |
$1,572
39,290
kWh
|
- | - | - | - | |
09 | 3.1191: Change procedures / equipment / operating conditions | $2,736 | $2,479 | - | - | - | - | $2,736 | |
10 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $612 | $2,154 |
$612
15,312
kWh
|
- | - | - | - | |
11 | 2.7124: Make a practice of turning off lights when not needed | $100 | $90 |
$100
2,500
kWh
|
- | - | - | - | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,015 | $700 |
$10,015
250,376
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $163,055 | $359,773 |
$27,600
689,992
kWh
|
$510
-
kW-mo/yr
|
$7,546 |
$124,663
-
MMBtu
|
$2,736 | ||
TOTAL IMPLEMENTED | $155,509 | $325,298 |
$27,600
689,992
kWh
|
$510
-
kW-mo/yr
|
- |
$124,663
-
MMBtu
|
$2,736 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs