ITAC Assessment: UC2509
ITAC logo
ITAC Assessment: UC2509
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Metallized films
NAICS 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing
SIC 3675: Electronic Capacitors
Sales Range $5
M
to 10
M
# of Employees 42
Plant Area 126,000
ft2
Annual Production 493,000
lb
Production Hrs. Annual 4,000
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $489,816 3,123,412
kWh
Electricity Demand $112,654 11,555
kW-mo/yr
Electricity Fees $36,525 -
Fuel Oil #2 $152,753 7,431
MMBtu
TOTAL YEARLY COSTS $791,748
RECOMMENDED SAVINGS* $146,877 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $28,237 - - - - $28,237
02 2.8123: Pay utility bills on time $114 - - - - $114
03 2.3212: Optimize plant power factor $19,546 $32,370 - - - $19,546
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,936 $100 $2,511
16,011
kWh
$425
-
kW-mo/yr
- -
05 2.1224: Replace boiler $42,258 $132,297 - - $42,258
-
MMBtu
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,269 $1,190 $2,269
14,469
kWh
- - -
07 2.2511: Insulate bare equipment $8,347 $2,798 - - $8,347
-
MMBtu
-
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $29,692 $9,100 $27,361
174,499
kWh
$2,331
-
kW-mo/yr
- -
09 2.6231: Utilize controls to operate equipment only when needed $13,478 $50 $13,478
85,955
kWh
- - -
TOTAL RECOMMENDED $146,877 $177,904 $45,619
290,934
kWh
$2,756
-
kW-mo/yr
$50,605
-
MMBtu
$47,897
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs