ITAC Assessment: TN0576
ITAC logo
ITAC Assessment: TN0576
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Wooden kitchen and bath cabinet doors and frames
NAICS
n/a
SIC 2434: Wood Kitchen Cabinets
Sales Range $10
M
to 50
M
# of Employees 114
Plant Area 208,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 4,410
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $119,688 3,737,397
kWh
Electricity Demand $88,351 10,397
kW-mo/yr
Natural Gas $47,192 10,077
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,171 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,304

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings
01 2.6242: Minimize operation of equipment maintained in standby condition $5,797 $1,200 $5,797
186,987
kWh
- - - - -
02 3.5315: Lease / purchase baler; sell cardboard to recycler $3,097 $8,640 - - - $2,050
-
lb
$2,640
-
lb
$(-1,593.0)
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,810 $1,890 $836
26,964
kWh
$974
-
kW-mo/yr
- - - -
04 2.1122: Re-size charging openings or add a movable door on equipment $1,791 - - - $1,791
-
MMBtu
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $867 $215 $109
3,517
kWh
$758
-
kW-mo/yr
- - - -
06 2.7261: Install timers and/or thermostats $809 $420 $809
26,084
kWh
- - - - -
TOTAL RECOMMENDED $14,171 $12,365 $7,551
243,552
kWh
$1,732
-
kW-mo/yr
$1,791
-
MMBtu
$2,050
-
lb
$2,640
-
lb
$(-1,593.0)
TOTAL IMPLEMENTED $13,304 $12,150 $7,442
240,035
kWh
$974
-
kW-mo/yr
$1,791
-
MMBtu
$2,050
-
lb
$2,640
-
lb
$(-1,593.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs