Assessment Year | 2025 |
---|---|
Principal Product | Copper and Aluminum Conductors, electrical insulation and steel components |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 287 |
Plant Area |
207,000
ft2
|
Annual Production | 10,239,108
units
|
Production Hrs. Annual | 5,408
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $257,056 | 3,696,832 |
kWh
|
$0.070 | |
Electricity Demand | $131,776 | 9,517 |
kW-mo/yr
|
$13.85 | |
Electricity Fees | $13,723 | - |
|
- | |
Natural Gas | $19,851 | 8,413 |
MMBtu
|
$2.36 | |
Waste Disposal Costs | |||||
Water Usage | $2,997 | 777 |
Tgal
|
$3.86 | |
Water Disposal | $6,585 | 775 |
Tgal
|
$8.50 | |
Other Liquid (non-haz) | $26,786 | 1 |
gal
|
$26,786.00 | |
TOTAL YEARLY COSTS | $458,774 | ||||
RECOMMENDED SAVINGS* | $30,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $3,656 | $1,015 |
$2,524
36,313
kWh
|
$1,132
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,150 | - |
$1,491
21,431
kWh
|
$659
-
kW-mo/yr
|
- | - | |
03 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $2,839 | $947 |
$1,918
27,594
kWh
|
- | - |
$921
-
MMBtu
|
|
04 | 2.3212: Optimize plant power factor | $13,183 | $15,550 | - | - | $13,183 | - | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,113 | - | - |
$8,113
-
kW-mo/yr
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $1,029 | $4,975 |
$(-65.0)
(-934)
kWh
|
$(-29.0)
-
kW-mo/yr
|
- |
$1,123
-
MMBtu
|
|
TOTAL RECOMMENDED | $30,970 | $22,487 |
$5,868
84,404
kWh
|
$9,875
-
kW-mo/yr
|
$13,183 |
$2,044
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs