ITAC Assessment: OK1146
ITAC logo
ITAC Assessment: OK1146
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Propane cylinders
NAICS 332439: Other Metal Container Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $50
M
to 100
M
# of Employees 140
Plant Area 130,000
ft2
Annual Production 30,500,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $787,061 19,676,536
kWh
Electricity Demand $732,550 31,850
kW-mo/yr
Electricity Fees $88,838 -
Natural Gas $724,806 120,801
MMBtu
Other Gas $14,919 1
MMBtu
Waste Disposal Costs
Water Usage $14,615 1,423
Tgal
Water Disposal $20,891 1,423
Tgal
Other Liquid (non-haz) $120 1
gal
TOTAL YEARLY COSTS $2,383,800
RECOMMENDED SAVINGS* $137,539 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $13,156 $11,709 - - - $13,156
02 2.2437: Recover waste heat from equipment $1,894 $152 - - $1,894
-
MMBtu
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,188 - $1,188
29,696
kWh
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,445 $2,615 $18,445
461,126
kWh
- - -
05 2.4239: Eliminate or reduce compressed air usage $723 $621 $723
18,068
kWh
- - -
06 2.1131: Repair faulty insulation in furnaces, boilers, etc $1,394 $1,913 - - $1,394
-
MMBtu
-
07 2.7211: Clean and maintain refrigerant condensers and towers $878 $1,980 $878
21,946
kWh
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $20,326 $16,391 $12,598
314,956
kWh
$7,728
-
kW-mo/yr
- -
09 2.9114: Use solar heat to make electricty $12,341 $218,400 $12,341
308,523
kWh
- - -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $67,194 $36,360 $67,194
1,679,850
kWh
- - -
TOTAL RECOMMENDED $137,539 $290,141 $113,367
2,834,165
kWh
$7,728
-
kW-mo/yr
$3,288
-
MMBtu
$13,156
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs