1,777

matching recommendations
$
$
ID Description Yearly
Savings
Imp
Cost
OR0791 #03 Y:2024 Optimize plant power factor $2,606 $17,324
OR0791 #02 Y:2024 Utilize energy-efficient belts and other improved mechanisms $1,032 -
OR0789 #05 Y:2024 Install common header on compressors $16,245 $4,904
OR0789 #03 Y:2024 Replace fossil fuel equipment with electrical equipment $4,115 $1,800
OR0789 #02 Y:2024 Optimize plant power factor $1,616 $14,338
OR0787 #03 Y:2024 Eliminate or reduce compressed air usage $4,379 $1,271
OR0788 #06 Y:2024 Install / repair insulation on steam lines $2,489 $150,000
OR0788 #05 Y:2024 Insulate glazing, walls, ceilings, and roofs $3,766 $200,000
OR0788 #04 Y:2024 Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $6,183 $30,000
OR0788 #03 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $7,448 $150,000
OR0788 #02 Y:2024 Replace hydraulic / pneumatic equipment with electric equipment $25,469 $250,000
ORC012 #04 Y:2023 Use computer programs to optimize hvac performance $2,567 $2,500
ORC012 #03 Y:2023 Reduce space conditioning during non-working hours $2,013 $6,000
ORC012 #02 Y:2023 Install occupancy sensors $375 $2,500
ORC012 #01 Y:2023 Utilize higher efficiency lamps and/or ballasts $669 $45,400
ORC013 #04 Y:2023 Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown $27,579 $200,000
ORC013 #03 Y:2023 Reduce space conditioning during non-working hours $9,215 $1,500
ORC013 #02 Y:2023 Install occupancy sensors $559 $1,200
ORC013 #01 Y:2023 Utilize higher efficiency lamps and/or ballasts $5,643 $49,125
OR0785 #04 Y:2023 Size electric motors for peak operating efficiency $2,475 $16,140