ITAC Assessment: OR0792
ITAC logo
ITAC Assessment: OR0792
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Meat
NAICS 311612: Meat Processed from Carcasses
SIC 2011: Meat Packing Plants
Sales Range $100
M
to 500
M
# of Employees 552
Plant Area 453,000
ft2
Annual Production 30,000,000
lb
Production Hrs. Annual 4,250
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,290,325 22,140,366
kWh
Electricity Demand $152,610 53,416
kW-mo/yr
Electricity Fees $200,333 -
Natural Gas $1,428,158 196,998
MMBtu
TOTAL YEARLY COSTS $4,071,426
RECOMMENDED SAVINGS* $466,054 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $1,993 - $1,993
19,261
kWh
- - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $15,081 $1,119 $14,062
135,930
kWh
$1,019
-
kW-mo/yr
- - -
03 2.7447: Install vinyl strip / high speed / air curtain doors $37,200 $18,409 $37,200
359,593
kWh
- - - -
04 2.2136: Install / repair insulation on steam lines $6,357 $3,090 - - $6,357
-
MMBtu
- -
05 3.4111: Use closed cycle process to minimize waste water production $7,380 $6,624 - - $1,984
-
MMBtu
- $5,396
06 2.7135: Install occupancy sensors $2,667 $3,106 $2,667
25,777
kWh
- - - -
07 4.231: Purchase equipment instead of leasing $395,376 $1,242,029 - - - $395,376 -
TOTAL RECOMMENDED $466,054 $1,274,377 $55,922
540,561
kWh
$1,019
-
kW-mo/yr
$8,341
-
MMBtu
$395,376 $5,396
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs