Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,123

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
SJ0034 #04 Y:2025 Use power during off-peak periods $1,270 -
SJ0032 #06 Y:2024 Turn off equipment when not in use $123 -
SJ0032 #04 Y:2024 Install an uninteruptable power supply $5,400 $34,907
SJ0032 #01 Y:2024 Install equipment to utilize waste fuel $129,492 $206,023
SF0630 #05 Y:2024 Use solar heat to make electricty $235,065 $1,065,176
SD0665 #06 Y:2024 Replace existing chiller with high efficiency model $74,386 $209,425
SD0665 #05 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $3,342 $2,233
SD0665 #04 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $58,983 $101,750
SD0665 #03 Y:2024 Adopt in-house material generation $23,739 $46,406
SD0665 #02 Y:2024 Use battery storage for demand control $203,574 $5,892
SD0665 #01 Y:2024 Use solar heat to make electricty $614,791 $395,505
SJ0030 #08 Y:2024 Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $663 $4,755
SJ0030 #07 Y:2024 Reduce the pressure of compressed air to the minimum required $4,287 -
SJ0030 #02 Y:2024 Use battery storage for demand control $18,627 $195,217
SJ0030 #01 Y:2024 Use solar heat to make electricty $630,866 $6,247,450
SD0664 #09 Y:2024 Reduce the pressure of compressed air to the minimum required $2,377 $250
SD0664 #08 Y:2024 Install direct acting units in place of compressed air pressure system in safety system $16,147 $6,200
SD0664 #07 Y:2024 Eliminate leaks in inert gas and compressed air lines/ valves $1,187 $1,186
SD0664 #06 Y:2024 Replace obsolete burners with more efficient ones $15,250 $16,600
SD0664 #05 Y:2024 Adopt in-house material generation $107,677 $47,756