ITAC Assessment: SD0661
ITAC logo
ITAC Assessment: SD0661
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Semiconductor Materials
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 185
Plant Area 62,600
ft2
Annual Production 12
units
Production Hrs. Annual 6,120
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,178,437 7,491,443
kWh
Electricity Demand $974,250 13,749
kW-mo/yr
Natural Gas $361,040 45,900
MMBtu
Waste Disposal Costs
Other Liquid (haz) $1,037,400 1,820,000
gal
TOTAL YEARLY COSTS $4,551,127
RECOMMENDED SAVINGS* $2,836,669 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $641,754 $589,764 $315,797
1,085,960
kWh
$325,957
-
kW-mo/yr
- - -
02 2.3141: Use battery storage for demand control $1,321,862 $54,390 $(-172,786.3)
(-594,176)
kWh
$1,494,648
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,348 $676 $908
3,121
kWh
$434
-
kW-mo/yr
- - $7
04 2.3132: Recharge batteries on during off-peak demand periods $3,584 $4,191 - $3,584
-
kW-mo/yr
- - -
05 2.3132: Recharge batteries on during off-peak demand periods $10,205 - - $10,205
-
kW-mo/yr
- - -
06 2.3132: Recharge batteries on during off-peak demand periods $2,354 - - $2,354
-
kW-mo/yr
- - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $854 $250 $854
2,935
kWh
- - - -
08 4.212: Adopt in-house material generation $809,075 $47,546 $(-11,949.0)
(-41,090)
kWh
$(-5,709.7)
-
kW-mo/yr
- $826,734
-
gal
-
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,243 $7,340 $5,192
17,854
kWh
$12,051
-
kW-mo/yr
- - -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,652 $2,148 $5,178
17,806
kWh
$2,474
-
kW-mo/yr
- - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $970 $1,863 $656
2,257
kWh
$314
-
kW-mo/yr
- - -
12 2.1243: Use heat from boiler blowdown to preheat boiler feed water $12,725 $11,775 - - $12,725
-
MMBtu
- -
13 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,043 $19,842 $4,766
16,388
kWh
$2,277
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $2,836,669 $739,785 $148,615
511,055
kWh
$1,848,588
-
kW-mo/yr
$12,725
-
MMBtu
$826,734
-
gal
$7
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs