936
matching recommendations
$
$
ARC | 2+ Digits Required | |
NAICS | 3+ Digits Required | |
SIC | 2+ Digits Required | |
3+ Characters Required for Products |
ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
LM0125 #04 Y:2007 | 04 | 2007 | Use heat in flue gases to preheat products or materials | $62,618 | $40,000 | |
LM0125 #03 Y:2007 | 03 | 2007 | Install equipment to move product | $89,704 | $11,000 | |
LM0125 #02 Y:2007 | 02 | 2007 | Install back-up equipment | $20,000 | $20,000 | |
LM0125 #01 Y:2007 | 01 | 2007 | Utilize higher efficiency lamps and/or ballasts | $2,003 | $2,604 | |
LM0124 #06 Y:2006 | 06 | 2006 | Begin a practice of predictive / preventative maintenance | $34,678 | $2,000 | |
LM0124 #05 Y:2006 | 05 | 2006 | Modify process to reduce material use/cost | $44,787 | $1,000 | |
LM0124 #04 Y:2006 | 04 | 2006 | Install sensors to detect and avoid jams | $15,120 | $1,400 | |
LM0124 #03 Y:2006 | 03 | 2006 | Schedule deliveries according to demand | $151,200 | $2,000 | |
LM0124 #02 Y:2006 | 02 | 2006 | Eliminate or reduce compressed air usage | $2,223 | $1,300 | |
LM0124 #01 Y:2006 | 01 | 2006 | Purchase new equipment to reduce material use / cost | $7,858 | $2,500 | |
LM0123 #04 Y:2006 | 04 | 2006 | Train operators for maximum operating efficiency | $37,630 | $1,000 | |
LM0123 #03 Y:2006 | 03 | 2006 | Replace existing hvac unit with high efficiency model | $6,789 | $20,000 | |
LM0123 #02 Y:2006 | 02 | 2006 | Cover open tanks | $7,790 | $1,800 | |
LM0123 #01 Y:2006 | 01 | 2006 | Utilize higher efficiency lamps and/or ballasts | $15,533 | $33,000 | |
LM0122 #05 Y:2006 | 05 | 2006 | Modify workload | $9,311 | $4,850 | |
LM0122 #04 Y:2006 | 04 | 2006 | Eliminate/reduce redundant inspections | $19,128 | $5,500 | |
LM0122 #03 Y:2006 | 03 | 2006 | Install occupancy sensors | $1,465 | $3,975 | |
LM0122 #02 Y:2006 | 02 | 2006 | Isolate hot or cold equipment | $814 | $2,000 | |
LM0122 #01 Y:2006 | 01 | 2006 | Replace existing hvac unit with high efficiency model | $42,830 | $89,250 | |
LM0121 #04 Y:2006 | 04 | 2006 | Insulate bare equipment | $3,734 | $3,100 |