Assessment Year | 2007 |
---|---|
Principal Product | aluminum ingots |
NAICS | 331314: Secondary Smelting and Alloying of Aluminum |
SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
Sales Range | $10 M to 50M |
# of Employees | 20 |
Plant Area |
20,000
ft2
|
Annual Production | 18,000,000
lb
|
Production Hrs. Annual | 5,280
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,169 | 306,202 |
kWh
|
$0.18 |
Electricity Demand | $16,063 | 1,054 |
kW-mo/yr
|
$15.24 |
Electricity Fees | $7,148 | - |
|
- |
Natural Gas | $236,628 | 26,278 |
MMBtu
|
$9.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $174,325 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $91,707 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,003 | $2,604 |
$1,182
12,192
kWh
|
$821
-
kW-mo/yr
|
- | - | - | |
02 | 4.651: Install back-up equipment | $20,000 | $20,000 | - | - | - | - | $20,000 | |
03 | 4.445: Install equipment to move product | $89,704 | $11,000 |
$2,640
28,509
kWh
|
- |
$23,064
-
MMBtu
|
$64,000 | - | |
04 | 2.2424: Use heat in flue gases to preheat products or materials | $62,618 | $40,000 | - | - |
$62,618
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $174,325 | $73,604 |
$3,822
40,701
kWh
|
$821
-
kW-mo/yr
|
$85,682
-
MMBtu
|
$64,000 | $20,000 | ||
TOTAL IMPLEMENTED | $91,707 | $13,604 |
$3,822
40,701
kWh
|
$821
-
kW-mo/yr
|
$23,064
-
MMBtu
|
$64,000 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs