Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

99

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Fluid milk
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
OR0672 #03 Y:2016 Use or replace with energy efficient substitutes $39,775 $138,248
OR0672 #02 Y:2016 Increase amount of condensate returned $21,014 $35,396
OR0672 #01 Y:2016 Use adjustable frequency drive or multiple speed motors on existing system $30,924 $26,614
OR0594 #06 Y:2012 Insulate bare equipment $2,867 $2,708
OR0594 #05 Y:2012 Install automatic stack damper $3,989 $5,325
OR0594 #04 Y:2012 Utilize higher efficiency lamps and/or ballasts $7,684 $7,360
OR0594 #03 Y:2012 Install anaerobic digester $1,369,423 $3,468,069
OR0594 #02 Y:2012 Use or replace with energy efficient substitutes $163,282 $119,416
OR0594 #01 Y:2012 Install an uninteruptable power supply $393,360 $20,880
OR0583 #06 Y:2012 Re-size charging openings or add movable cover or door $2,779 $6,600
OR0583 #05 Y:2012 Install / repair insulation on steam lines $1,391 $3,854
OR0583 #04 Y:2012 Establish burner maintenance schedule for boilers $6,078 $500
OR0583 #03 Y:2012 Utilize higher efficiency lamps and/or ballasts $6,663 $19,592
OR0583 #02 Y:2012 Re-size charging openings or add movable cover or door $2,994 $10,000
OR0583 #01 Y:2012 Avoid frost formation on evaporators $3,140 $2,412
OR0518 #03 Y:2007 Insulate bare equipment $840 $4,100
OR0518 #02 Y:2007 Install occupancy sensors $1,020 $2,050
OR0518 #01 Y:2007 Minimize contamination of water before treatment $51,600 $120,000
OR0309 #12 Y:1997 Schedule deliveries according to demand $62,300 $51,600
OR0309 #11 Y:1997 Schedule deliveries according to demand $4,240 -