Assessment Year | 2012 |
---|---|
Principal Product | Milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $100 M to 500M |
# of Employees | 135 |
Plant Area |
91,000
ft2
|
Annual Production | 6,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $964,549 | 15,292,580 |
kWh
|
$0.063 |
Electricity Demand | $162,883 | 32,582 |
kW-mo/yr
|
$5.00 |
Electricity Fees | $85,777 | - |
|
- |
Natural Gas | $785,883 | 189,171 |
MMBtu
|
$4.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,940,605 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,377,107 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.631: Install an uninteruptable power supply | $393,360 | $20,880 | - | - | - | - | $393,360 | - | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $163,282 | $119,416 |
$101,413
1,570,108
kWh
|
$16,869
-
kW-mo/yr
|
- | - | $45,000 | - | - | |
03 | 2.9141: Install anaerobic digester | $1,369,423 | $3,468,069 | - | - |
$37,288
-
MMBtu
|
$53,866
-
lb
|
- | $(-14,192.0) | $1,292,461 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,684 | $7,360 |
$5,868
90,855
kWh
|
- | - | - | $978 | $838 | - | |
05 | 2.1123: Install automatic stack damper | $3,989 | $5,325 |
$3,989
61,766
kWh
|
- | - | - | - | - | - | |
06 | 2.2511: Insulate bare equipment | $2,867 | $2,708 | - | - |
$2,867
-
MMBtu
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,940,605 | $3,623,758 |
$111,270
1,722,729
kWh
|
$16,869
-
kW-mo/yr
|
$40,155
-
MMBtu
|
$53,866
-
lb
|
$439,338 | $(-13,354.0) | $1,292,461 | ||
TOTAL IMPLEMENTED | $1,377,107 | $3,475,429 |
$5,868
90,855
kWh
|
- |
$37,288
-
MMBtu
|
$53,866
-
lb
|
$978 | $(-13,354.0) | $1,292,461 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs