ITAC Assessment: WV0692
ITAC logo
ITAC Assessment: WV0692
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Mining equipment
NAICS 333131: Mining Machinery and Equipment Manufacturing
SIC 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 157,500
ft2
Annual Production 5,000
ton
Production Hrs. Annual 4,680
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $204,944 2,134,694
kWh
Electricity Demand $85,340 8,089
kW-mo/yr
Electricity Fees $6,437 -
Natural Gas $12,772 1,442
MMBtu
TOTAL YEARLY COSTS $309,493
RECOMMENDED SAVINGS* $63,669 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,143 $26,880 $10,942
113,982
kWh
$5,201
-
kW-mo/yr
- -
02 2.4224: Upgrade controls on compressors $11,868 $3,963 $9,174
95,566
kWh
$2,694
-
kW-mo/yr
- -
03 2.6231: Utilize controls to operate equipment only when needed $11,521 $1,560 $8,989
93,638
kWh
$2,532
-
kW-mo/yr
- -
04 2.2449: Recover heat from exhausted steam, hot air or hot water $10,047 $5,250 - - $10,047
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,941 $1,452 $3,854
40,150
kWh
$1,087
-
kW-mo/yr
- -
06 2.4221: Install compressor air intakes in coolest locations $2,255 $4,690 $1,487
15,490
kWh
$422
-
kW-mo/yr
$346
-
MMBtu
-
07 2.7241: Install outside air damper / economizer on hvac unit $2,230 $10,710 $1,966
20,475
kWh
$264
-
kW-mo/yr
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,619 $64 $1,260
13,123
kWh
$359
-
kW-mo/yr
- -
09 2.4239: Eliminate or reduce compressed air usage $1,281 $1,420 $996
10,374
kWh
$285
-
kW-mo/yr
- -
10 2.4157: Establish a predictive maintenance program $1,059 $3,300 $1,314
13,686
kWh
$369
-
kW-mo/yr
- $(-624.0)
11 2.1233: Analyze flue gas for proper air/fuel ratio $705 $1,346 - - $705
-
MMBtu
-
TOTAL RECOMMENDED $63,669 $60,635 $39,982
416,484
kWh
$13,213
-
kW-mo/yr
$11,098
-
MMBtu
$(-624.0)
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs