| Assessment Year | 2025 |
|---|---|
| Principal Product | Industrial Pipe |
| NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
| SIC | 3498: Fabricated Pipe and Pipe Fittings |
| Sales Range | $10 M to 50M |
| # of Employees | 87 |
| Plant Area |
161,437
ft2
|
| Annual Production | 20,800
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,993 | 587,000 |
kWh
|
$0.12 |
| Electricity Demand | $17,753 | 3,659 |
kW-mo/yr
|
$4.85 |
| Fuel Oil #2 | $38,513 | 1,683 |
MMBtu
|
$22.88 |
| TOTAL YEARLY COSTS | $125,259 | |||
| RECOMMENDED SAVINGS* | $61,811 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $61,811 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $1,382 | $525 |
$1,382
11,711
kWh
|
- | - | |
| 02 | 2.8117: Install sub-metering equipment | $3,463 | $3,000 |
$3,463
29,350
kWh
|
- | - | |
| 03 | 2.1321: Replace fossil fuel equipment with electrical equipment | $44,252 | $192,732 |
$(-3,240.0)
(-27,456)
kWh
|
$15,492
-
MMBtu
|
$32,000 | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $12,714 | $65,000 |
$(-9,595.0)
(-81,314)
kWh
|
$22,309
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $61,811 | $261,257 |
$(-7,990.0)
(-67,709)
kWh
|
$37,801
-
MMBtu
|
$32,000 | ||
| TOTAL IMPLEMENTED | $61,811 | $261,257 |
$(-7,990.0)
(-67,709)
kWh
|
$37,801
-
MMBtu
|
$32,000 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs