Assessment Year | 2023 |
---|---|
Principal Product | Automation Positioning Equipment |
NAICS | 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing |
SIC | 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 123 |
Plant Area |
50,000
ft2
|
Annual Production | 50,000
ton
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,401 | 998,757 |
kWh
|
$0.061 |
Electricity Demand | $6,454 | 2,297 |
kW-mo/yr
|
$2.81 |
Electricity Fees | $908 | - |
|
- |
Natural Gas | $6,505 | 1,705 |
MMBtu
|
$3.82 |
TOTAL YEARLY COSTS | $75,268 | |||
RECOMMENDED SAVINGS* | $11,375 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,422 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,119 | $24,727 |
$4,453
72,403
kWh
|
$666
-
kW-mo/yr
|
- | - | |
02 | 2.6232: Install set-back timers | $1,981 | $1,274 |
$938
15,254
kWh
|
$216
-
kW-mo/yr
|
$827
-
MMBtu
|
- | |
03 | 2.4224: Upgrade controls on compressors | $1,083 | $5,364 |
$979
15,912
kWh
|
$104
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $835 | $218 |
$734
11,936
kWh
|
$101
-
kW-mo/yr
|
- | - | |
05 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $751 | $3,668 | - | - |
$751
-
MMBtu
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $540 | $1,161 |
$(-9.0)
(-146)
kWh
|
- |
$549
-
MMBtu
|
- | |
07 | 2.4239: Eliminate or reduce compressed air usage | $517 | $1,081 |
$455
7,398
kWh
|
$62
-
kW-mo/yr
|
- | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $367 | $219 |
$322
5,239
kWh
|
$45
-
kW-mo/yr
|
- | - | |
09 | 2.4151: Develop a repair/replace policy | $182 | $646 |
$233
3,741
kWh
|
$31
-
kW-mo/yr
|
- | $(-82.0) | |
TOTAL RECOMMENDED | $11,375 | $38,358 |
$8,105
131,737
kWh
|
$1,225
-
kW-mo/yr
|
$2,127
-
MMBtu
|
$(-82.0) | ||
TOTAL IMPLEMENTED | $4,422 | $4,599 |
$2,673
43,422
kWh
|
$455
-
kW-mo/yr
|
$1,376
-
MMBtu
|
$(-82.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs