Assessment Year | 2010 |
---|---|
Principal Product | Paper Board |
NAICS | 322130: Paperboard Mills |
SIC | 2631: Paperboard Mills |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
250,000
ft2
|
Annual Production | 12,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $641,649 | 16,336,800 |
kWh
|
$0.039 |
Electricity Demand | $510,871 | 30,396 |
kW-mo/yr
|
$16.81 |
Other Gas | $336,544 | 26,944 |
MMBtu
|
$12.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $235,626 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $139,827 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $61,713 | $37,440 | - | - |
$61,713
-
MMBtu
|
- | - | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $57,379 | $6,240 | - | - |
$57,379
-
MMBtu
|
- | - | |
03 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $38,419 | $128,000 |
$(-3,932.0)
(-99,114)
kWh
|
$(-2,286.0)
-
kW-mo/yr
|
$47,637
-
MMBtu
|
$(-3,000.0) | - | |
04 | 2.4151: Develop a repair/replace policy | $19,593 | $1,638 |
$12,552
316,407
kWh
|
$7,275
-
kW-mo/yr
|
- | $(-234.0) | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,792 | $7,958 |
$9,993
251,891
kWh
|
$5,799
-
kW-mo/yr
|
- | - | - | |
06 | 2.7313: Recycle air for heating, ventilation and air conditioning | $11,226 | $20,400 |
$(-2,420.0)
(-60,993)
kWh
|
$(-1,412.0)
-
kW-mo/yr
|
$21,058
-
MMBtu
|
- | $(-6,000.0) | |
07 | 2.7293: Install dry sprinkler system or other method to reduce heating requirements | $7,432 | $16,240 | - | - |
$7,432
-
MMBtu
|
- | - | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $6,432 | $2,028 | - | - |
$6,432
-
MMBtu
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,622 | $312 |
$3,554
89,594
kWh
|
$2,068
-
kW-mo/yr
|
- | - | - | |
10 | 2.4312: Improve lubrication practices | $3,683 | $858 |
$2,330
58,736
kWh
|
$1,353
-
kW-mo/yr
|
- | - | - | |
11 | 2.4221: Install compressor air intakes in coolest locations | $3,378 | $936 |
$2,134
53,800
kWh
|
$1,244
-
kW-mo/yr
|
- | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,182 | $2,886 |
$1,820
45,885
kWh
|
$1,362
-
kW-mo/yr
|
- | - | - | |
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,239 | $1,000 |
$785
19,780
kWh
|
$454
-
kW-mo/yr
|
- | - | - | |
14 | 2.4239: Eliminate or reduce compressed air usage | $536 | $52 |
$536
13,507
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $235,626 | $225,988 |
$27,352
689,493
kWh
|
$15,857
-
kW-mo/yr
|
$201,651
-
MMBtu
|
$(-3,234.0) | $(-6,000.0) | ||
TOTAL IMPLEMENTED | $139,827 | $168,876 |
$10,336
260,550
kWh
|
$5,985
-
kW-mo/yr
|
$132,506
-
MMBtu
|
$(-3,000.0) | $(-6,000.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs