ITAC Assessment: WM0027
ITAC logo
ITAC Assessment: WM0027
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Ceiling Tiles
NAICS 327993: Mineral Wool Manufacturing
SIC 3296: Mineral Wool
Sales Range $10
M
to 50
M
# of Employees 42
Plant Area 138,000
ft2
Annual Production 27,000,000
units
Production Hrs. Annual 2,967
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,269 1,296,000
kWh
Electricity Demand $66,351 7,806
kW-mo/yr
Electricity Fees $20,805 -
Natural Gas $60,716 10,924
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $138,982 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,499

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,697 $644 $1,764
27,134
kWh
$933
-
kW-mo/yr
- - -
02 2.4221: Install compressor air intakes in coolest locations $1,649 $276 $1,119
17,205
kWh
$530
-
kW-mo/yr
- - -
03 2.4224: Upgrade controls on compressors $8,153 $5,600 $8,153
125,425
kWh
- - - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $8,126 $1,240 - - $8,126
-
MMBtu
- -
05 2.7131: Add area lighting switches $191 $400 $191
2,934
kWh
- - - -
06 3.5313: Increase amount of waste recovered for resale $344 $1,545 - - - $344
-
lb
-
07 4.426: Modify workload $53,406 - - - - - $53,406
08 2.6231: Utilize controls to operate equipment only when needed $11,010 $7,260 $6,332
97,412
kWh
$4,678
-
kW-mo/yr
- - -
09 4.446: Automate finishing process $53,406 $11,000 - - - - $53,406
TOTAL RECOMMENDED $138,982 $27,965 $17,559
270,110
kWh
$6,141
-
kW-mo/yr
$8,126
-
MMBtu
$344
-
lb
$106,812
TOTAL IMPLEMENTED $12,499 $6,520 $11,036
169,764
kWh
$1,463
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs