ITAC Assessment: WI0162
ITAC logo
ITAC Assessment: WI0162
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product BEAUTY SALON EQUIPMENT
NAICS
n/a
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 130
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,750
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $192,136 2,407,386
kWh
Natural Gas $33,671 17,819
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,284 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,105

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,560 $5 $1,514
19,050
kWh
- $46
02 2.6232: Install set-back timers $590 $1,200 $590
7,327
kWh
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,457 $1,749 $1,457
18,171
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $774 $1,280 $774
9,672
kWh
- -
05 2.1233: Analyze flue gas for proper air/fuel ratio $152 $500 - $152
-
MMBtu
-
06 2.7261: Install timers and/or thermostats $132 $800 - $132
-
MMBtu
-
07 2.3132: Recharge batteries on during off-peak demand periods $265 - $265
-
kWh
- -
08 2.7447: Install vinyl strip / high speed / air curtain doors $215 $150 - $215
-
MMBtu
-
09 2.2511: Insulate bare equipment $139 $480 - $139
-
MMBtu
-
TOTAL RECOMMENDED $5,284 $6,164 $4,600
54,220
kWh
$638
-
MMBtu
$46
TOTAL IMPLEMENTED $3,105 $2,415 $2,553
28,722
kWh
$506
-
MMBtu
$46
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs