Assessment Year | 1989 |
---|---|
Principal Product | STAINLESS STEEL CASTINGS |
NAICS |
n/a
|
SIC | 3324: Steel Investment Foundries |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $575,568 | 11,001,466 |
kWh
|
$0.052 |
Natural Gas | $154,847 | 43,395 |
MMBtu
|
$3.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,899 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,333 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,497 | $17,166 |
$6,497
-
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $208 | $300 |
$208
4,103
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,614 | $1,003 |
$1,614
30,774
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,828 | - |
$1,828
34,877
kWh
|
- | |
05 | 2.6232: Install set-back timers | $801 | $400 |
$801
15,240
kWh
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $880 | $1,000 |
$880
16,706
kWh
|
- | |
07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $594 | $800 | - |
$594
-
MMBtu
|
|
08 | 2.7261: Install timers and/or thermostats | $241 | $250 | - |
$241
-
MMBtu
|
|
09 | 2.3132: Recharge batteries on during off-peak demand periods | $236 | - |
$236
-
kWh
|
- | |
TOTAL RECOMMENDED | $12,899 | $20,919 |
$12,064
101,700
kWh
|
$835
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,333 | $3,503 |
$3,739
66,823
kWh
|
$594
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs