Assessment Year | 1989 |
---|---|
Principal Product | DISTILLED BOTTLED WATER |
NAICS |
n/a
|
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 105 |
Plant Area |
n/a
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $132,388 | 2,128,664 |
kWh
|
$0.062 |
Natural Gas | $74,912 | 15,858 |
MMBtu
|
$4.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,902 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $51,883 | $300,000 |
$79,306
1,274,912
kWh
|
$(-27,423.0)
-
MMBtu
|
|
02 | 2.7442: Keep doors and windows shut when not on use | $11,109 | $6,000 | - |
$11,109
-
MMBtu
|
|
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,165 | $15,000 | - |
$9,165
-
MMBtu
|
|
04 | 2.2441: Preheat boiler makeup water with waste process heat | $6,568 | $8,000 | - |
$6,568
-
MMBtu
|
|
05 | 2.7261: Install timers and/or thermostats | $5,346 | $750 | - |
$5,346
-
MMBtu
|
|
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,916 | - |
$2,916
-
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,143 | $1,243 |
$1,143
18,464
kWh
|
- | |
08 | 2.4312: Improve lubrication practices | $1,989 | - |
$1,989
31,946
kWh
|
- | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $691 | - |
$691
11,137
kWh
|
- | |
10 | 2.4221: Install compressor air intakes in coolest locations | $523 | $750 |
$523
8,499
kWh
|
- | |
11 | 2.6218: Turn off equipment when not in use | $500 | $800 | - |
$500
-
MMBtu
|
|
12 | 2.6232: Install set-back timers | $317 | $400 |
$317
4,982
kWh
|
- | |
TOTAL RECOMMENDED | $92,150 | $332,943 |
$86,885
1,349,940
kWh
|
$5,265
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,902 | $3,193 |
$7,056
66,529
kWh
|
$5,846
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs