| Assessment Year | 2016 |
|---|---|
| Principal Product | Dried Milk Products |
| NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
| SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
| Sales Range | $100 M to 500M |
| # of Employees | 72 |
| Plant Area |
83,190
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $976,304 | 21,368,692 |
kWh
|
$0.046 |
| Electricity Demand | $232,402 | 34,556 |
kW-mo/yr
|
$6.73 |
| Electricity Fees | $5,884 | - |
|
- |
| Natural Gas | $1,222,906 | 322,575 |
MMBtu
|
$3.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,565 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,647 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2113: Repair or replace steam traps | $13,590 | $12,584 | - | - |
$13,590
-
MMBtu
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,026 | $744 |
$3,026
66,234
kWh
|
- | - | - | - | |
| 03 | 2.8123: Pay utility bills on time | $2,153 | $213 | - | - | - | - | $2,153 | |
| 04 | 2.6124: Establish equipment maintenance schedule | $1,079 | $4,500 |
$1,079
23,622
kWh
|
- | - | - | - | |
| 05 | 2.7224: Reduce space conditioning during non-working hours | $418 | $14 |
$325
7,117
kWh
|
- |
$93
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $220 | $585 |
$193
4,233
kWh
|
$27
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $161 | $43 |
$161
3,533
kWh
|
- | - | - | - | |
| 08 | 3.4157: Replace water cooling on processes with air cooling | $9,918 | $88,300 |
$398
8,720
kWh
|
- | - |
$9,520
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $30,565 | $106,983 |
$5,182
113,459
kWh
|
$27
-
kW-mo/yr
|
$13,683
-
MMBtu
|
$9,520
-
Tgal
|
$2,153 | ||
| TOTAL IMPLEMENTED | $20,647 | $18,683 |
$4,784
104,739
kWh
|
$27
-
kW-mo/yr
|
$13,683
-
MMBtu
|
- | $2,153 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs