| Assessment Year | 1986 |
|---|---|
| Principal Product | KNITTED SOCKS |
| NAICS |
n/a
|
| SIC | 2252: Hosiery, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 107 |
| Plant Area |
n/a
|
| Annual Production | 800,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $92,767 | 1,240,328 |
kWh
|
$0.075 |
| LPG | $11,041 | 1,486 |
MMBtu
|
$7.43 |
| Fuel Oil #2 | $20,373 | 3,469 |
MMBtu
|
$5.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,994 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,603 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $119 | $92 |
$119
1,758
kWh
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $417 | - |
$417
5,569
kWh
|
- | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $391 | $250 | - |
$(-431.0)
-
MMBtu
|
$822
-
MMBtu
|
|
| 04 | 2.2511: Insulate bare equipment | $272 | $320 | - |
$(-297.0)
-
MMBtu
|
$569
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $691 | $400 | - |
$691
-
MMBtu
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,644 | $600 |
$1,644
21,981
kWh
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $460 | $100 |
$460
6,155
kWh
|
- | - | |
| TOTAL RECOMMENDED | $3,994 | $1,762 |
$2,640
35,463
kWh
|
$(-37.0)
-
MMBtu
|
$1,391
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,603 | $1,350 |
$2,521
33,705
kWh
|
$260
-
MMBtu
|
$822
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs