ITAC Assessment: AT0060
ITAC logo
ITAC Assessment: AT0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product KNITTED SOCKS
NAICS
n/a
SIC 2252: Hosiery, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 107
Plant Area
n/a
Annual Production 800,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,767 1,240,328
kWh
LPG $11,041 1,486
MMBtu
Fuel Oil #2 $20,373 3,469
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,994 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,603

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Fuel Oil #2 Savings
01 2.4133: Use most efficient type of electric motors $119 $92 $119
1,758
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $417 - $417
5,569
kWh
- -
03 2.2136: Install / repair insulation on steam lines $391 $250 - $(-431.0)
-
MMBtu
$822
-
MMBtu
04 2.2511: Insulate bare equipment $272 $320 - $(-297.0)
-
MMBtu
$569
-
MMBtu
05 2.2437: Recover waste heat from equipment $691 $400 - $691
-
MMBtu
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,644 $600 $1,644
21,981
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $460 $100 $460
6,155
kWh
- -
TOTAL RECOMMENDED $3,994 $1,762 $2,640
35,463
kWh
$(-37.0)
-
MMBtu
$1,391
-
MMBtu
TOTAL IMPLEMENTED $3,603 $1,350 $2,521
33,705
kWh
$260
-
MMBtu
$822
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs