ITAC Assessment: UD0161
ITAC logo
ITAC Assessment: UD0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product CORRUGATED CONTAINERS
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 165
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $272,071 4,961,899
kWh
Natural Gas $310,732 55,808
MMBtu
LPG $18,749 2,121
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $109,278 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,890

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.8114: Change rate schedules or other changes in utility service $26,916 $40,000 $26,916
-
kWh
-
02 2.8114: Change rate schedules or other changes in utility service $3,600 $3,000 $3,600
-
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,398 $10,864 $4,263
79,719
kWh
$(-865.0)
-
MMBtu
04 2.4323: Use optimum size and capacity equipment $861 $1,000 $861
26,964
kWh
-
05 2.1123: Install automatic stack damper $9,744 $1,377 $2,684
47,773
kWh
$7,060
-
MMBtu
06 2.6218: Turn off equipment when not in use $8,671 $2,100 - $8,671
-
MMBtu
07 2.2443: Re-use or recycle hot or cold process exhaust air $23,960 $48,000 - $23,960
-
MMBtu
08 2.2414: Use waste heat from hot flue gases to preheat $32,128 $40,000 - $32,128
-
MMBtu
TOTAL RECOMMENDED $109,278 $146,341 $38,324
154,456
kWh
$70,954
-
MMBtu
TOTAL IMPLEMENTED $36,890 $61,964 $5,124
106,683
kWh
$31,766
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs