Assessment Year | 2011 |
---|---|
Principal Product | Cleaning and Sanitization Products |
NAICS | 325611: Soap and Other Detergent Manufacturing |
SIC | 2841: Soap and Other Detergents, Except Specialty Cleaners |
Sales Range | $10 M to 50M |
# of Employees | 52 |
Plant Area |
49,500
ft2
|
Annual Production | 75,000
Tgal
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,859 | 843,072 |
kWh
|
$0.082 |
Electricity Demand | $20,010 | 2,235 |
kW-mo/yr
|
$8.95 |
Natural Gas | $4,267 | 315 |
MMBtu
|
$13.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,484 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,515 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,515 | $1,000 |
$5,152
62,833
kWh
|
$2,363
-
kW-mo/yr
|
- | |
02 | 2.4226: Use / purchase optimum sized compressor | $3,000 | $8,500 |
$975
11,896
kWh
|
$618
-
kW-mo/yr
|
$1,407 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $781 | $8,625 |
$435
5,304
kWh
|
$277
-
kW-mo/yr
|
$69 | |
04 | 2.7135: Install occupancy sensors | $188 | $175 |
$188
2,288
kWh
|
- | - | |
TOTAL RECOMMENDED | $11,484 | $18,300 |
$6,750
82,321
kWh
|
$3,258
-
kW-mo/yr
|
$1,476 | ||
TOTAL IMPLEMENTED | $10,515 | $9,500 |
$6,127
74,729
kWh
|
$2,981
-
kW-mo/yr
|
$1,407 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs