| Assessment Year | 2005 |
|---|---|
| Principal Product | Steel Castings |
| NAICS | 331513: Steel Foundries (except Investment) |
| SIC | 3325: Steel Foundries, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 85 |
| Plant Area |
210,000
ft2
|
| Annual Production | 3,000
ton
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $187,290 | 5,708,846 |
kWh
|
$0.033 |
| Electricity Demand | $129,904 | 8,979 |
kW-mo/yr
|
$14.47 |
| Electricity Fees | $32,217 | - |
|
- |
| Natural Gas | $398,682 | 58,809 |
MMBtu
|
$6.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,738 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $42,009 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.1192: Reduce scrap production | $34,320 | $7,500 | - | - | - |
$34,320
-
lb
|
|
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,442 | $1,000 | - | - |
$4,442
-
MMBtu
|
- | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $3,729 | $3,000 | - | - |
$3,729
-
MMBtu
|
- | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $3,247 | $1,000 |
$1,901
57,946
kWh
|
$1,346
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $45,738 | $12,500 |
$1,901
57,946
kWh
|
$1,346
-
kW-mo/yr
|
$8,171
-
MMBtu
|
$34,320
-
lb
|
||
| TOTAL IMPLEMENTED | $42,009 | $9,500 |
$1,901
57,946
kWh
|
$1,346
-
kW-mo/yr
|
$4,442
-
MMBtu
|
$34,320
-
lb
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs