Assessment Year | 2001 |
---|---|
Principal Product | Mining Equipment |
NAICS |
n/a
|
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 182 |
Plant Area |
138,000
ft2
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $91,607 | 3,498,692 |
kWh
|
$0.026 |
Electricity Demand | $73,311 | 7,799 |
kW-mo/yr
|
$9.40 |
Electricity Fees | $16,057 | - |
|
- |
Natural Gas | $137,343 | 24,907 |
MMBtu
|
$5.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $108,903 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $31,173 | $2,000 | - | - |
$31,173
-
MMBtu
|
- | - | - | - | - | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $10,170 | $8,874 |
$(-361.0)
(-13,090)
kWh
|
- |
$10,531
-
MMBtu
|
- | - | - | - | - | |
03 | 2.3134: Shift from daytime to nighttime operation | $24,740 | - | - |
$25,053
-
kW-mo/yr
|
- | - | - | $(-313.0) | - | - | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $10,208 | $4,500 | - | - | - | - | - | - | - | $10,208 | |
05 | 2.4322: Use or replace with energy efficient substitutes | $12,894 | $62,046 |
$5,749
208,313
kWh
|
$7,145
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 3.8142: Distill contaminated solvents for reuse | $6,914 | $4,000 | - | - | - |
$4,363
-
gal
|
$(-582.0)
-
lb
|
$(-2,045.0) | - | $5,178 | |
07 | 3.7137: Replace cloth rags with paper towels | $6,301 | - | - | - | - | - |
$(-78.0)
-
lb
|
- | $6,379 | - | |
08 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $3,805 | $11,500 | - | - |
$3,805
-
MMBtu
|
- | - | - | - | - | |
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,549 | - | - | - | - | - |
$1,549
-
lb
|
- | - | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,149 | $2,009 |
$542
19,634
kWh
|
$607
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $108,903 | $94,929 |
$5,930
214,857
kWh
|
$32,805
-
kW-mo/yr
|
$45,509
-
MMBtu
|
$4,363
-
gal
|
$889
-
lb
|
$(-2,358.0) | $6,379 | $15,386 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs